JUDGEMENT
-
(1.) Heard learned counsel appearing for the plaintiff.
(2.) This is a suit for decree for a sum of Rs.58,78,180/- together with interim interest and interest upon judgment @ 18% per annum with other reliefs. Plaint
case in brief is that plaintiff is engaged in business of manufacture and sale of
forged and machined components which are supplied to Tata Motors Limited and
its sub-vendors. The defendant being the nodal agency of the State of West
Bengal allotted a plot of land measuring 1.82 acres of land within Tata Small Car
Project at Singur, West Bengal by its letter dated 7th august, 2008 and such
document was confirmed for the plot no. B4-B for a period of 99 years by the
defendant at the Tata Small Car Project sites and a possession certificate dated
8th August, 2008 was also given to the plaintiff and duly confirmed by the letter dated 11th August, 2008. Plaintiff intimated about the possession certificate to
Tata Motors Limited with a request for construction of rule leading to the said
plot to set up its unit. Thereafter, plaintiff obtained trade licence and no objection
certificate from the concerned authorities. It is submitted that plaintiff applied for
sanction of the loan with the defendant for the purpose of carrying costs for the
said project and the loan applied for Rs.5,80,55,000/- but no step was taken by
the defendant to extend any help towards sanction of loan or for the purpose of
setting of the unit. The defendant continued to take the plea that the land at
Singur which was acquired by Government had become a political issue and the
matter had reached as impasse that it was not possible for setting of the units.
So, obviously the project could not proceed and the plaintiff suffered loss which
is intimated by a letter dated 12th August, 2013 to the defendant for the refund of
a sum of Rs.27,30,000/- which were deposited as costs for allotment of the land
at Vendor Park, Tata Small Car Project sites, Singur, Hooghly, West Bengal. The
plaintiff issued several remainders by its letters dated 12th August, 2013, 5th
September, 2013 and 31st October, 2016 but the payment under deposit was not
refunded on the representation by the defendant that the fate of the project was
not finally decided and the matter was pending before the Hon'ble Supreme
Court of India and the plaintiff was asked to wait for sometime. Ultimately, the
Hon'ble Supreme Court in its judgment dated 31st August, 2016 set aside the
acquisition of the land so obviously the plaintiff could not get the allotment of the
land for the purpose of setting of the unit rather it is stood terminated by
frustration.
(3.) Accordingly, the plaintiff has claimed a sum of Rs.58,78,180/- as on 6th February, 2017 from the defendant as the particulars mentioned in paragraph 14
of the plaint.;
Click here to view full judgement.
Copyright © Regent Computronics Pvt.Ltd.