STATE Vs. BENGAL BUILDERS
LAWS(CAL)-1988-11-4
HIGH COURT OF CALCUTTA
Decided on November 17,1988

STATE Appellant
VERSUS
BENGAL BUILDERS Respondents

JUDGEMENT

- (1.) THIS is an application for setting aside an award dated Feb. 10, 1988 made and published by Mr. P.C.. Majumdar, the Sole Arbitrator. There is also a prayer for condonation of delay under S.5 of the Limitation Act in making this application for setting aside the award.
(2.) THE learned arbitrator made an award for a sum of Rs. 5,05,000/- in favour of the respondent, Bengal Builders. THE learned arbitrator also made an award for interest at 9% per annum on the said sum of Rs. 5,05,000/- for the period from the date of entering upon the reference by the learned arbitrator, i.e. April 27, 1987, till the date of payment or decree by the competent court, whichever is earlier. THE learned arbitrator made the said award for Rs. 5,05,000/- in full and fianl settlement of all the claims and counter-claims of the parties, which had been referred to the arbitrator. The material portion of the impugned award is as follows : - "FIRSTLY That I award and direct the respondent, the State of West Bengal, shall pay to the claimant M/s. Bengal Builders in the present case, a sum of Rs. 5,05,000.00/- (Rupees Five Lakhs and five thousand) only in full and final settlement of all the claims and counter-claims of the Parties which have been referred to me. All the claims and counter-claims of the Parties are merged into and extinguished by the said sum of Rs. 5,05,000.00/- (Rupees Five Lakhs and Five Thousand) only. SECONDLY That I award and direct the respondent, State of West Bengal, shall pay to the claimant M/s. Bengal Builders, interest on the said sum of Rs. 5,05,000.00/- (Rupees Five Laks and Five Thousand) only at the rate of 9 (Nine) Per Cent per annum from date of entering into reference by me, i.e. 27th. April 1987, till the date of payment or decree by the competent Court, whichever is earlier."
(3.) ONE Debasis Das on behalf of the State-respondent by an affidavit affirmed on April 8, 1988 has stated that the notice for filing of the award dt. Feb. 10, 1988 was received by the respondent on Feb. 24, 1988. The Notice of Motion was taken out on March 31, 1988. According to the period prescribed by the laws of limitation, the Notice of Motion should have been taken out by March 24, 1988. So there has been a delay for a few more days. By way of an explanation the said Debasis Das has stated in his said affidavit that the said notice was addressed to the Executive Engineer, Irrigation and Waterways Directorate, Teesta Barrage Division No. I at his office at Oodlabari, District Jalpaiguri. According to the said deponent, as the notice was received at the end of the financial year it was not possible for the respondent to take action on the said notice. He has further stated that after arranging for some urgent matters the said notice was duly forwarded to the Advocate-on-record for the State of West Bengal with instruction to draw and file a petition for setting aside the said award. As stated earlier, the Notice of Motion was taken out on March 31, 1988.;


Click here to view full judgement.
Copyright © Regent Computronics Pvt.Ltd.