JUDGEMENT
V.S.SIRPURKAR, C.J. -
(1.) This is an application under Section 11 of
the Arbitration & Conciliation Act, 1996
(hereinafter referred to as the Act), for appointment
of an arbitrator. There was a contract between the petitioners herein and the
Union of India, represented by Divisional
Engineer (Co-ordination), Eastern Railway,
Sealdah. The petitioner company was
awarded a contract of lifting of track from
km 5/25 to km 8/21 all four lines, and PQS
station limit for provision of ballast cushion
with other ancillary works at a cost of Rs.
12,33,968/-. This contract was awarded to
the petitioner company vide letter dated 14th
April, 2004. The work was to be completed
within four months from the date of Issue of
the contract. In pursuance of this offer an
agreement was executed on 13th
September, 2004. It seems that the petitioner
company's claim is that due to default and
breaches on the part of the respondents the
execution of the work was prolonged and
the extensions were also granted by the
respondents without any penalty and when
the work in question was successfully executed
to the extent of 90% before the expiry of the
extended period, a notice was sent
to the petitioner company making some
allegations. The petitioner company had given
reply to the notice. However, it seems that
the petitioner company has not been paid
for the financial losses suffered by it on account
of breach of contract by the respondents. The petitioner company by its letter
dated 22nd February, 2005 claimed that its
dues should be paid. However, no reply was
ever received by the petitioner company.
(2.) Thus since this contract took place
within the local jurisdiction of this Court,
this Court has the territorial Jurisdiction to
try and entertain this application and there
is also a live issue in between the parties.
Clause 63(1)(i) of the agreement provides for
the arbitration clause, which is as under :
"63(l)(i) - Demand for Arbitration.
In the event of any dispute or difference
between the parties hereto as to the construction or operation of this contract, or
the respective rights and liabilities of the
parties on any matter in question, dispute
or difference on any account or as to the
withholding by the Railway of any certificate
to which the contractor may claim to
be entitled to, or if the Railway fails to make
a decision within 120 days, then and in any
such case but except in any of the 'excepted
matters' referred to in Clause 62 of these
conditions, the contractor, after 120 days
but within 180 days of his presenting his
final claim on disputed matters, shall
demand in writing that the dispute or difference be referred to arbitration."
(3.) Thus, there is a valid arbitration clause
in the agreement between the parties. The
petitioner company's case is that in pursuance
of this clause, the petitioner company
sent a letter dated 22nd February, 2005
mentioning therein that in case nothing was
heard or the letter was not complied with,
the petitioner company would be compelled
to Invoke the arbitration agreement. It is an
admitted position that the Divisional Railway
Manager, to whom this letter was sent,
received this letter and in that letter the
petitioner company had claimed a sum of
Rs. 22,03,317/-. However, there was no decision
taken even within 120 days, as provided in the arbitration agreement, and the
petitioner company therefore by letter dated
11th July, 2005 invoked the arbitration
clause and requested the General Manager
to refer the dispute to the arbitration as per
the arbitration clause quoted above. It is
apparent that no action was taken and
therefore the petitioner company filed the
present application.;
Click here to view full judgement.
Copyright © Regent Computronics Pvt.Ltd.