E AND N E F RLY CO OP BANK LTD Vs. B GUHA AND CO
LAWS(CAL)-1985-2-6
HIGH COURT OF CALCUTTA
Decided on February 14,1985

E.AND N.E.F.RLY.CO-OP.BANK LTD. Appellant
VERSUS
B.GUHA AND CO Respondents

JUDGEMENT

- (1.) THIS is an application under Ss. 30 and 33 of the Arbitration Act, 1940 for setting aside an Award dt. 11th July, 1983 made by a sole arbitrator in respect of disputes and claims arising out of Agreement No. PRE-34-A/ V-1 dt. 27th March, 1971.
(2.) THE respondent entered into an agreement being Contract No. PRE-34-4/ V-1 dt. 27th March, 1971 with the petitioner for construction, addition and alteration of the building at Nos.34A and 34B Sashi Bhusan Dey Street, Calcutta. By a subsequent agreement dt. 30th June, 1972 the rates of work mentioned in the agreement dt. 27th March, 1971 were revised and the date of the completion of the work was extended till 15th September, 1972. The works under the said contract were completed on or about 31st March, 1973. By a letter dt. 23rd Aug., 1973 addressed to the petitioner the respondent claimed from the petitioner the final bill amount of Rs. 40,950.49 p. and refund of security deposit. By another letter dt. 8th Jan., 1974 addressed to the petitioner the respondent made a further claim of Rs. 58,500/- under the head "Other claims and dues". This figure was later on revised upon giving full particulars by the letter dt. 1st March, 1974 to a sum of Rs. 57,563.01 p. By a letter dt. 3rd September, 1974 the petitioner informed the respondent that the said claim of Rs. 57,563.01 p. was placed before the Board of Directors of the petitioner Bank for consideration and the Board was unable to consider as there was no work order for the work for which the said bill was presented. In a meeting held thereafter on 5th April, 1975 between the parties it was stated by the respondent that there were some addition and alteration work which had to be attended on the instruction for which said Bill for Rs. 59,563.01 p. was submitted and there was no work order for the said work. The petitioner, however, denied and disputed the validity and legality of the said claim of the respondent, and as such refused to make any payment in respect thereof. The petitioner paid the other sums claimed by the respondent.
(3.) THE disputes and differences arose between the parties which were referable to the arbitration under an Arbitration Agreement contained in the said contract between the parties. THE respondent made an application in this Court under S. 20 of the Arbitration Act for filing of the said arbitration agreement and for reference of said disputes and differences. THE said application was marked as Special Suit No. 24 of 1976. By an order dt. 24th Jan., 1976 this Court directed filing of the said arbitration agreement and further ordered that all matters and differences in the special suit be referred to the arbitration of an arbitrator to be appointed in terms of the said arbitration agreement. An appeal preferred by the petitioner from the said order was dismissed by the Court of Appeal.;


Click here to view full judgement.
Copyright © Regent Computronics Pvt.Ltd.