JUDGEMENT
SOUMEN SEN, J. -
(1.) THE petitioner has filed this application for setting aside of an award
under Section 34 of the Arbitration and Conciliation Act, 1996
(hereinafter referred to as the "said Act").
(2.) THE arbitration proceeding is arising out of a tripartite settlement arrived at between the parties on 17th February, 2005.
The learned Arbitrator in the said reference had also passed an interim
award which is, however, not subject matter of challenge in this
proceeding.
(3.) THE petitioner has challenged the award in so far as it relates to the execution of the work under three different work orders at the Gurgaon
office of the petitioner executed under the work orders being Nos: - (I)
HO/04/CE(1)/018 Dated 04.03.2004 amounting to Rs.2,70,61,540/ - (II)
HO/04/CE(D)/ 39 Dated 13.04.2004 amounting to Rs.1,00.83,750/ - (III)
HO/04/CE/060 Dated 28.06.2004 amounting to Rs.18,59,547/ -
In the statement of claim filed before the arbitrator, the claimant stated that following an invitation of interest and rates for the
electrical works of the whole building issued by the architect the
claimant expressed his interest and made tentative offer to architect
(TAG) on March 27, 2004 by its letter bearing reference no. RDG/78/03
dated 27th March, 2004. The two other contractors had also submitted
their offer. However, on evaluation of the offer, the petitioner accepted
the offer submitted by the claimant.;
Click here to view full judgement.
Copyright © Regent Computronics Pvt.Ltd.