JUDGEMENT
D.K.Seth, J. -
(1.) The petitioner had submitted a plan for sanction for
the purpose of construction of six storeyed building to the Howrah Municipal
Corporation on 25th May, 1984. On 8th June, 1984, a resolution was taken by the
Building Committee that the sanction be recommended on payment of sanction
fee of Rs. 4,500/- subject to removal of certain objections. This was communicated
to the petitioner by a letter dated 16th August, 1984 addressed by the Howrah
Municipal Corporation. It is alleged by Mr. Banerjee that the defects were
removed on 22nd August, 1987. On perusal of the notesheet, it appears that
after this recommendation was made for removal of the defects on 8th June,
1984 the next note is for calculation of the sanction fee at the present rate
endorsed on 29th July, 1987. Accordingly the enhanced sanction fee calculated
and forwarded for further order to the Commissioner on 3rd August, 1987. The
Commissioner enquired whether the condition for sanction has been fulfilled
by the party. After this note, it appears from the record that the defects were
removed. Mr. Mukherjee submits that this is the whole record, which is produced
before the Court. He has also submitted that attempt was made to trace out the
corrected plan but that was not available on record. We had also browsed through
the record and the file produced before us, but we are unable to find out any
corrected plan on record. Whereas there is another note dated 22nd August,
1987, where it has been noted that the party had fulfilled the conditions of
sanction laid down in the meeting and the party may now be asked to deposit
the sanction fee at the present rate within 30 days for sanction of the plan. It
appears that there was a note to discuss the matter on 5th October, 1987. There
is another note that the matter was discussed. This particular record was torn,
we are unable to read the note dated 28th August, 1987. The only part that we
could read is 'be approved', which appears to have been signed by the same
person who had signed the note on 8th August, 1987 which seems to be that of
the Commissioner.
1.1. It appears that after this episode the writ petitioner respondent wrote a
letter on 10th June, 1989 seeking permission to deposit the sanction fee on the
ground that the writ petition had left for his native place and therefore, he
could not deposit the sanction fee. This letter is on record. It appears from the
said letter that the writ petitioners were the owners of the property for which
they had submitted a plan for six storeyed building upon which this plan was
sanctioned with direction to deposit sanction fee. That the petitioners had left
for their native village outside Bengal for a long period of time due to some
bona fide reasons as such they could not deposit the sanction fees towards plan
and could not obtain the plan sanctioned from the Municipality. They want to
execute the construction work according to the sanctioned plan on payment of
usual charges towards plan as assessed at the present rate. Therefore, he prayed
that he may be allowed to deposit the sanction fee. This letter was placed before
the Commissioner on 12th June, 1989. On 19th June, 1989 there was a note by
the Commissioner as to whether the plan was sanctioned as per Building Rules.
By a note dated 17th July, 1989, it was pointed out that the case was placed
before the Building Committee so that the proposal may be sanctioned according
to C. M. Act, which was continued when the original meeting was held. On 18th
July, 1989, it was decided by the authority that it was a proposal for six storeyed
building and since the sanction fee was not deposited pursuant to the sanction
order dated 8th June, 1984, the same cannot be acted upon after expiry of more
than 5 (five) years and the party may submit a fresh plan in accordance with
the Building Rules. This appears to have been signed by the Mayor. Accordingly,
the petitioner was informed on 7th September, 1989 that since the sanction fee
was not deposited, therefore, the plan was cancelled.
1.2. Against this order on 11th March, 1990, the writ petition being C. O. No.
14149(W) of 1989 was moved. However, no interim order was granted, on 7th
September, 1990 when the matter came up again, an order was passed
permitting the petitioner to deposit the sanction fee at the enhanced rate within
a fortnight and upon acceptance of such amount the Municipality was to proceed
in accordance with law. It is contended by Mr. Banerjee appearing for the
respondents that this amount was deposited through a demand draft. But Mr.
Mukherjee appearing on behalf of the Howrah Municipal Corporation/appellant
submits that no deposit was ever made. From the record, it appears that the
issuing bank was enquired about whether the cheque was encashed, by a letter
dated 7th February, 1996 addressed by the writ petitioners. This was replied to
in the negative by the bank. A xerox copy of this letter dated 19th February,
1996 addressed to the writ petitioner/respondent by the bank pursuant to its
letter dated 7th February, 1996, is already on record of the Howrah Municipal
Corporation. Much has been said about the deposit and non-deposit of this
demand draft. But we are not on this question since this was an action pendente
lite which would depend on the final outcome of the matter.
The question:
(2.) Now the question, in the facts and circumstances as disclosed above, is
whether the Howrah Municipal Corporation is obliged to sanction the plan and
permit the writ petitioners to construct six storeyed building in accordance
with the provisions of the Howrah Municipal Act as was applicable to the case
of sanction prior to the coming into force of the new Act. Mr. Banerjee contends
that there was no communication to his client that the writ petitioner was
required to deposit the sanction fee within 30 days. According to him, until this
is communicated, the writ petitioner is entitled to deposit the amount and carry
on construction on the basis of the plan already sanctioned on 8th June, 1984 as
corrected on 22nd August, 1987 in compliance of the sanction order. However,
this is being opposite by Mr. Mukherjee.
The Building Rules : Its application :
(3.) In order to appreciate the situation, we may refer to the Building Rules
applicable in 1984 or prior to the new Act, which came into force with effect from
18th December, 1989. Admittedly, this was governed by the Howrah Municipal
(Temporary Provisions) Act, 1933 by which the provisions of the Calcutta
Municipal Act, 1923 was adopted and extended to the Municipality of Howrah.
This adoption continued even with the enactment of Calcutta Municipal Act,
1951 by reason of section 614 thereof and also with the Calcutta Municipal
Corporation Act, 1980 by reason of section 633 thereof. The Howrah Municipal
Act, 1965 also did not affect these provisions. Therefore, it is the same Building
Rules, which became applicable by reason of section 633 of the Calcutta Municipal
Corporation Act, 1980 would be applicable in this case as on 8th June, 1984.
3.1. The Building Rules provides in Part 7, the procedure for sanction of a
new building. Various procedures have been mentioned therein, we need not go
into those. Rule 57 requires sanction of a plan or refusal thereof, which runs as
follows:
"57. (1) Within fifteen days after the receipt of any application made under
Rule 52 for permission to execute any work, or of any information or
documents required under this schedule, or within fifteen days after the
Commissioners have been satisfied that there are no objections which may
lawfully be taken to the grant of permission to execute the work,
the Commissioners shall, by written order, either-
(a) grant permission conditionally or unconditionally to execute the work, or
(b) refuse, on one or more of the grounds mentioned in Rule 59 or Rule 63,
as the case may be, to grant such permission.
(2) When the Commissioners grant permission conditionally under clause
(a) of sub-rule (1), they may in regard thereto impose such conditions,
consistent with the Calcutta Municipal Act, 1923, as enforced in the
Municipality of Howrah, as they may think fit.
(3) Notwithstanding anything contained in sub-rules (1) and (2), in any case
in which it appears to the Commissioners that any public improvements
which may render necessary the acquisition of the site of a proposed building
or any part thereof are desirable and expedient, they may withhold sanction
to the building plans submitted in respect of such building for a period not
exceeding three months from the date of such submission".
3.2. In view of Rule 57, it is well within the power of the Municipality to
impose condition while granting sanction. If conditions are fulfilled, the sanction
is granted. Until the conditions are fulfilled, the sanction cannot be effective.
But as soon as the conditions are complied with, the sanction would become
valid from the date when the conditions were stipulated for sanction. This
condition may also include rectifications, if required, as pre-condition for
sanction.
3.3. In case the Municipality neither sanctions nor refuses the sanction,
then under Rule 58(1) the applicant is entitled to proceed to execute the work
without contravening any provisions of the Calcutta Municipal Act, 1923 as
enforced in the Municipality of Howrah or any rules or bye-laws made
thereunder. Rule 64 prescribes that when plan is sanctioned for construction of
a building, the construction is required to be completed within three years after
the date on which the permission is given to execute the work and the work
shall not be commenced or continued thereafter until a fresh application has
been made and a fresh permission is granted. Such fresh sanction order can be
obtained if such application is made before the expiry of three years with a
certificate that the construction of the building has been commenced and a
substantial portion of it is already completed; and then the Commissioner shall
thereupon cause the building to be inspected and if they consider that the
substantial portion of it has been completed they shall grant such a certificate
to that effect. Only then fresh permission can be granted on the fresh application.
3.4. In the present case, the sanction was granted on 8th June, 1984. Now
the question arises as to whether this particular date shall be taken to be the
date of sanction for the purpose of Rule 64. Both the learned Counsel had relied
upon the decision of a learned Single Judge in C. O. No. 710(W)of 1991 disposed
of on 25th September, 1992 by Hon'ble Ruma Pal, J. as Her Lordship then was,
in the case of Suniti Bhusan Palui vs. Howrah Municipal Corporation and in
C. 0. No. 3076 (W) of 1990, Jamuna Samanta vs. Howrah Municipal
Corporation, disposed of on 30th November, 1990 by Hon'ble Mukul Gopal
Mukherjee, J. as His Lordship then was. In both these decisions, it was held
that when a plan has been sanctioned before the date when the new Act has
come into force then the same is to be governed by the old Act and the mischief
of the new Act would not be applicable. In Suniti Bhusan Palui (supra) it was
held further that if there was no time limit even for the performance of the
subsequent conditions, in that event, whenever this subsequent conditions were
fulfilled the date of sanction would remain the date when the sanction was
accorded in that case it was 10th March, 1989 that the defects were removed
after the new Act had come into force. Similar view was taken in Jamuna
Samanta (supra); there also the defects were removed on 7th February, 1990
pursuant to the order passed on 11th March, 1989 which was held to be the date
of grant of sanction, a date prior to 18th December, 1989 when the Howrah
Municipal Corporation (Amendment) Ordinance, 1989 came into effect. Thus if
the date of original sanction subject to compliance of certain formalities is taken
to be the date of sanction and upon compliance of all formalities the date of
sanction would be the date when the sanction is accorded subject to compliance
of all formalities in that event in the present case, it would be 8th June, 1984
which would be the date of granting the sanction.
The date of sanction : Validity : Whether the old Act will apply or
the new:;