JUDGEMENT
PRASENJIT MANDAL, J. -
(1.) THIS application is at the instance
of the respondent and is directed against the order dated
March 1, 2013 passed by the learned Additional District
Judge, Sealdah in Misc. Appeal No.16 of 2013 thereby
disposing of an application for stay.
(2.) HAVING heard the learned Advocates of both the sides and on perusal of the materials on record, I find that
there is a dispute between the owner of the land and the
developer. By virtue of an agreement, the
developer/respondent started construction on the land of
the appellant. But, a dispute arose as to payment.
According to the owner of the land, he paid a sum of
Rs.4,30,000/- to the developer/respondent whereas the
work had been done by the developer to the tune of Rs.1.5
lakh only. Such an assessment had been done by a
certified engineer at the instance of the appellant.
Mr. Moinak Bose, learned Advocate appearing for the petitioner submits that unless stay is granted, the owner
of the land would be deprived from making any
construction on his own land.
(3.) MR . Shahjahan Hossain, learned Advocate appearing for the opposite party has referred to the provisions of
Sections 35, 14 & 16 of the Specific Relief Act. He has
also referred to the decision of AIR 1988 Delhi 162
relating to the provision of Section 42 of the Specific
Relief Act on negative covenant etc., 1986 (2) Current
Civil Cases 633 relating to grant of injunction and AIR
1993 Orisa 78 on an application under Order 39 Rule 1 and 2 when to be entertained ex parte.;
Click here to view full judgement.
Copyright © Regent Computronics Pvt.Ltd.