JUDGEMENT
-
(1.) THE Judgment of the Court was as follows : Both the claimant and the respondents in the reference seek the
annulment of the arbitral award, but to varying ends and extents. The
respondents in the reference say that the award rendered under the
Arbitration Act, 1940 is perverse and there are errors apparent on the
face thereof as no reasonable person, on the basis of the material as
carried by the parties to the reference, could have concluded that the
claimant in the reference was entitled to an order for specific
performance of the agreement between the parties. Though the
arbitrator, in exercise of the perceived discretion under Section 20 of
the Special Relief Act, 1963, did not direct specific performance of the
agreement but awarded damages in lieu thereof, the respondents in the
reference insist that since the claimant was not entitled to specific
performance there was no occasion for the claimant to be awarded
damages. The further ground urged by the respondents in the reference
(hereinafter referred to as the owners) is that the statement of claim did
not contain any relief for damages in lieu of specific performance nor
did the claimant quantify the alleged damages on such count. The owners
refer to the arbitrary conduct of the arbitrator in inviting a suggestion
from the claimant at the second-last sitting of the reference and passing
an award in damages in lieu of specific performance on the basis of the
claimant's unsubstantiated statement in a few loose sheets of paper
which the owners did not get a meaningful chance to deal with.
(2.) THE claimant's grievance, on the other hand, is that upon the arbitrator finding that the claimant was entitled to specific performance
of the agreement, specious grounds were proffered to deny the claimant
its rightful due. The claimant, however, admits that its statement of claim
in the reference did not indicate any relief for damages in lieu of specific
performance nor did the claimant quantify the damages on such score
in any subsequent pleadings. The claimant maintains that it is entitled
to specific performance. The claimant says that it had sought damages
in addition to specific performance of the agreement and submits that
the award of damages in lieu of specific performance by the arbitrator
can, in any event, not be sustained. The claimant has expressly agreed
to the award being set aside to the extent that it granted damages in
New of specific performance to the claimant, on the ground that given
the manner in which the award on such account was made, the claimant
is in no position to sustain it.
The agreement between the parties of June 28, 1989 envisaged the demolition of the existing structures at the Outram Street
premises and the construction of three buildings on the land measuring
about 37 cottah. A sketch-map was appended to the agreement and the
original agreement carved out three distinct portions of the land marked
in blue, pink and green. The claimant was obliged, under the agreement,
to construct, according to the plan sanctioned by the Calcutta Municipal
Corporation, a commercial building on the 23-cottah southern portion
of the premises, the constructed area whereof was to be shared by the
owners and the claimant; and, two buildings on about seven cottah land
each, one being exclusively for the owners and the other being
exclusively for the claimant. The agreement recorded that there was an
individual occupant at a part of the premises and a company functioned
thereat under the control of such individual.
(3.) THE claimant alleged in the reference that despite the claimant having performed its obligations under the agreement in, inter alia,
making the initial payment to the owners and causing the property to be
rid of the occupant, the owners did not permit the agreement to be
executed by discharging the obligations cast on the owners thereunder.
The owners cited the long delay on the part of the claimant and the
claimant's conduct amounting to lack of readiness and willingness on
its part to pursue the work under the agreement. The owners also
maintained that the claimant had failed to carry out its part of the bargain
and was, thus, not entitled to specific performance of the agreement
that the claimant had claimed.;
Click here to view full judgement.
Copyright © Regent Computronics Pvt.Ltd.