JUDGEMENT
PRASENJIT MANDAL,J. -
(1.) CHALLENGE is to the Order No. 157 dated July 8, 2009 passed by the learned Judge, City Civil Court, 2 nd
Bench,
Calcutta in Misc. Case No.1787 of 1993 arising out of the Title
Execution Case No.90 of 1986.
The opposite party got a decree relating to agreement for
lease on compromise in Title Suit No.150 of 1976 against the
petitioner and the said decree was put into execution being Title
Execution Case No.90 of 1986. In that Execution proceeding, the judgment-debtor filed an application under Section 47 of the CPC
and the said application was converted into the Misc. Case No.1787
of 1993.
(2.) BY the impugned order, the learned Executing Court allowed the said Misc. Case in part on contests and the learned Executing
Court has held that the decree-holder/opposite party herein is
entitled to get an accommodation of 2000 sq.ft out of 6000 sq.ft
and that it could put the decree into execution accordingly.
Being aggrieved, this application has been preferred.
Now, the question is whether the impugned order should be
sustained.
Having heard the learned Advocates of both the sides and on
perusal of the materials-on-record, it appears that the Title Suit
No.150 of 1976 was decreed on compromise in terms of the Solenama
on June 9, 1976. As per Solenama, the petitioner is bound to
deliver 6000 sq.ft of space to the opposite party upon certain
terms and conditions, such as, consideration money to be paid at
the rate of Rs.100.00 per sq.ft, etc. The bank was also required
to pay a sum of Rs.29,010.00 by way of rent.
Admittedly, for the purpose of construction of the new building in place of the old building, the opposite party/bank
advanced a sum of Rs.3,50,000.00 to finish the construction to the
petitioner. Admittedly, out of the 6000 sq.ft space, the bank got
possession of 4000 sq.ft. Under the circumstances, the petitioner
has contended that the decree-holder cannot put the decree into
execution for the entire 6000 sq.ft. It has also contended since
the bank made delay in making the payment, the rest space of 2000
sq.ft had been let out to a third party and at present, the
decree-holder cannot get the possession of that space.
While disposing of the said Misc. Case, the learned Executing
Court has held that the petitioner has failed to make it clear
before the Court when it completed the construction of the entire
6000 sq.ft of space on the first floor and when it asked the bank to take delivery of possession of that space, after taking payment
of the construction. It also failed to establish that the
petitioner had let out the rest 2000 sq. ft to the third party and
any way, the matter for execution of the case is being dragged
since 1986 till date.
(3.) THE petitioner has also contended that the opposite party has failed to pay the consideration in respect of the area over which
the bank already got possession and as such, a sum of
Rs.12,17,173.00 by way of consideration and interest became due and
payable as on March 31, 2003. In any way, the Executing Court
cannot go behind the decree.
In the instant case, the Execution Case has been filed for
recovery of possession and if the judgment-debtor has any claim in respect of money or other claims, such as, interest, etc, that is
a separate issue. The judgment-debtor may show that the decreeholder is still to discharge his obligations.
So far as the application under Section 47 of the CPC is
concerned, I find that execution of the decree is resisted on the
ground that the Execution Case is not maintainable on the ground
as recorded above as per contention of the petitioner. Since, the
Executing Court cannot go behind the decree, so far as the
findings of the learned Executing Court to the effect that the
decree-holder is still entitled to get an accommodation of 2,000
sq. ft of space out of 6000 sq.ft space and it could put the
decree into execution are concerned, in my view, these findings
cannot be wriggled out.;
Click here to view full judgement.
Copyright © Regent Computronics Pvt.Ltd.