BHUTORIA BROTHERS (P) LTD. Vs. BANWARILAL PURUSHOTTAM DASS & ORS.
LAWS(CAL)-1981-12-33
HIGH COURT OF CALCUTTA
Decided on December 24,1981

Bhutoria Brothers (P) Ltd. Appellant
VERSUS
Banwarilal Purushottam Dass And Ors. Respondents

JUDGEMENT

Anil Kumar Sen, J. - (1.) This is a revisional application at the instance of the defendant in a suit for declaration, permanent and mandatory injunction and damages. The revisional application is directed against an order dated July 29, 1981, passed by the learned District Judge, Howrah in Miscellaneous Appeal No. 19 of 1981 thereby affirming an order dated January 31, 1981, passed by the learned Munsif, 1st Court, Howrah, allowing the plaintiff's prayer for temporary mandatory for restoration of electric supply in the suit premises passed in Title Suit No. 298 of 1979.
(2.) The plaintiff is a lessee in respect of holding Nos. 130A and 130B, Dharamtala Street, Howrah, under a partnership firm, Chhotulal Jaharmul, being the proforma-defendant No. 4 in the aforesaid suit. According to the plaintiff they run a factory on the leasehold premises and for the said purpose were having electricity supplied through the defendant No. 1, Bhutoria Brothers, another partnership firm running their factory at holding No. 130, Dharamtala Street under an agreement. They had not only shared security deposit with the Calcutta Electric Supply Corporation for the bulk supply of electricity through the defendant No. 1, but they had been regularly paying for the electricity consumed by them which was limited to 94 H. P. The defendant No. 1 served a notice dated August 24, 1979, proposing to disconnect the supply of electricity on certain untenable grounds and when the plaintiff approached the defendant No. 1 they assured to reconsider their decision but suddenly on October 31, 1979, the defendant No. 1 disconnected the supply of electricity to the plaintiff. Such disconnection resulted in serious prejudice and irreparable loss to the plaintiff who at their factory had commitments to manufacture goods deliverable to national and international concerns. Hence, they instituted the aforesaid suit on November 20, 1979, and therein filed an application under Order 39, Rules 1 and 2 of the Code of Civil Procedure praying for immediate restoration of the supply of electricity pending the disposal of the suit. Such a prayer having been concurrently allowed by the two courts below, the defendant No. 1 has preferred the present revisional application.
(3.) Mr. Dutt, appearing in support of this revisional application, has challenged the orders passed by the two Courts below on the ground that such an order is clearly unsustainable in law and no Court could have granted such an interim mandatory injunction as prayed for. According to Mr. Dutt even upon the plaintiff's own case the defendant No. 1 committed a breach of their obligation under a contract when they disconnected electric supply with effect from October 31,1979, and when such an obligation is not specifically enforceable the plaintiff is, at best, entitled to damages so that an order of mandatory injunction by way of enforcement of such an obligation is not sustainable in law. Secondly, it has been contended by Mr. Dutt that the power of a Court to grant an interim mandatory order is limited to restoration of things as they were on the date of the suit and nothing more. In the present case, according to Mr. Dutt disconnection having been effected on October 31, 1979, and the suit having been filed 20 days thereafter the Court could have no jurisdiction to direct restoration of the electric supply by an order of temporary mandatory injunction.;


Click here to view full judgement.
Copyright © Regent Computronics Pvt.Ltd.