JUDGEMENT
-
(1.) This application under Section 482 of the Code of Criminal Procedure has
been taken out by Sanjiv Jajodia, an accused in Case No. C/1079 of 2010
pending in the Court of learned Metropolitan Magistrate, 10th
Court at
Calcutta praying for quashing of the proceeding against him under Section
63 of the Companies Act. The petitioner has also challenged the legality,
validity and propriety of the orders dated 13.1.2010 and 28.1.2010. A
reference to the factual aspect is required to be set out in order to
appreciate the matter effectively.
(2.) The petitioner was appointed as a Director of the said Chandi Steel
Industries Limited (hereinafter referred to as the company) on 20th
September 19993 and is continuing since then.The company came out
with a public issue of 55,00,000 equity shares of Rs. 10 each for cash at
par aggregating to Rs. 550 lacs during the year 2003 in terms of
prospectus dated 22nd
October 2003. The objects of the issue as it was
then envisaged and stated in the prospectus was to expand the installed
capacity of the plant from 10,800 MT to 44,000 MT per year at a capex of
Rs. 525 lakhs and to meet the issue expenses at an estimated cost of Rs.
25 lakhs. The entire fund requirement of Rs. 550 lacs was to be financed
from proceeds from the public issue. The prospectus was filed with the
Registrar of Companies, West Bengal on 22.10.2003. The said public issue
was opened on 3rd
November 2003 and was fully subscribed. On the public
issue being made, the company received the sum of Rs. 5, 50,00,000/-
(calls-in-arrear Rs. 39,000/- against the 55,00,000 equity shares of Rs. 10
each. As stated in the prospectus, a sum of Rs. 525 lacs was to be utilized
for expansion of the re-rolling mill of the company by increasing the
installed capacity from 108000 MT to 44000 MT per year and the project
was scheduled to be completed by March 2004 and commercial production
was to commence in April 2004. The Company was hopeful that it would be
able to implement during the year 2005-06 the expansion project for which
the public funds were collected. However, before the company could
proceed with further implementation of the project, it was observed that
further increase of re-rolling mill capacity was no more a viable option in
view of two major developments during the years 2004-2005 and 2005-
2006.
a. Inspite of the best efforts the Energy charges (power
cost) as a cost of production remained at a high level
which was affecting the viability of the project in the
given competitive market.
b. There was an increase in demand for secondary
rerolled steel products. Due to this increase, the
primary steel producers started setting up and
increasing capacities for producing rerolled
secondary steel products. This resulted in steep
market competition for the small-scale secondary
steel rerolling units.
(3.) The company has a smll-scale secondary steel rerolling unit. In view of
market factors as also the energy cost increasing manifold as aforesaid, the
Board of Directors of the Company at its meeting held on 25th
February
2006 considered it prudent to take a decision to abandon the Expansion
project of the Company as envisaged in the prospectus but modernize the
existing re-rolling facilities of the company to become efficient in the fact of
adverse market situations. Pursuant to the decision taken by the Board at
its meeting held on 25th
February 2006, an extraordinary general meeting
of the company was convened on 27th
March, 2006 to consider utilization
of the unutilized money amounting to Rs. 381.20 lacs raised through
public issue for the modernization of the existing manufacturing facilities
of the company instead of undertaking the expansions plans of the
company as envisaged in the prospectus. Such Extraordinary General
Meeting was held on 27th
March 2006 and requisite resolution was adopted
at the Extraordinary General Meeting of the shareholders of the company
on 27th
March 2006. By such Extraordinary General Meeting, the
shareholders of the company accorded consent to the management of the
company to utilize the balance sum of Rs. 381.20 lakhs raised through
such public offer in the year 2003 in the modernization scheme instead of
undertaking the expansion plan as stipulated therein. Pursuant to an in
terms of such resolution of the Extraordinary General Meeting, the
company undertook the modernization scheme instead of the expansion
plan. By a letter dated 12th
February 2007, the Deputy Registrar of
Companies, West Bengal called for information and explanation under
Section 234 of the Companies Act, 1956.The company sent a reply dated
10th
April 2007. In continuation of such reply, the company sent another
letter dated 17th
May 2007 to the Registrar of Companies, west Bengal. The
office of the Regional Director, Eastern Region, Ministry of Corporate
Affairs, Government of India, undertook inspection under Section 209 A of
the Companies Act, 1956. By a letter dated 11th
September 2008, the
Deputy Director (Inspection) alleged that the alleged violation of the
provisions of the Companies Act, 1956 had been noticed. By a letter dated
14th
November 2008, the company explained and clarified the allegations
levelled by the Deputy Director (Inspection) in the letter dated 11th
September 2008. The opposite party issued a three show cause notices
numbering 2756, 2757 and 2758 all dated 18th
December 2009 alleging
contravention of the provisions of Sections 63, 68 and 628 of the
Companies Act, 1956. The Company requested for time to reply thereto
and sought for extension till 15th
January 2010. However the opposite
party instituted a criminal case against the petitioner on the self same
material by filing a complaint being case no. C/1079/2010 filed by the
opposite party as the complainant in the Court of the Learned Chief
Metropolitan Magistrate at Kolkata against the petitioner .;
Click here to view full judgement.
Copyright © Regent Computronics Pvt.Ltd.