JUDGEMENT
GUHA, J. -
(1.) THIS appeal by the plaintiff arises out of a suit for recovery of arrears of increased pay amounting to Rs. 1327 -8 -0 and for additional provident fund dues of Rs. 1250. The facts which gave rise to the present litigation are briefly as follows.
(2.) THE plaintiff was an employee under the District Board of the 24 -parganas who are the defendants in this suit. He joined the service of the District Board on 1st June 1915. On 1st January 1920 a time scale for clerks was introduced, the time scale being Rs. 45/3/75 (efficiency bar) 21/2 -100. On 1st January 1922, the plaintiff was allowed to draw the pay of Rs. 66 and in June 1924 his pay became Rs. 72. He continued to draw the same say till June 1928, when he was transferred to Basirhat. From 1st August 1928 he drew pay at Rs. 82 -8 -0. From 1st June 1980 he drew pay at Rs. 87 -8 -0 but the amount was reduced by Rs. 2 -8 -0 with effect from 1st July 1930. From 1st July 1930 to 23rd April 1940 when he retired from service he continued to draw pay at the rate of Rs. 85 without having any increment during this period of about ten years. The plaintiff's grievance was twofold. He claimed that some arrears in pay were due to him under the rules and secondly, he claimed that though by a resolution of the District Board on 22nd May 1940 confirmed on 19th June 1940 he was entitled to additional provident fund money, no such sum was paid to him till the institution of the suit which was filed on 7th May 1943. The defence of the District Board was briefly to the effect that the plaintiff was not entitled to any arrears of pay as he had not crossed the efficiency bar. As regards the claim in respect of the provident fund, the defence inter alia was that the claim was premature. On both the points the lower Courts have found in favour of the defendant and dismissed the plaintiff's suit accordingly.
It is urged on behalf of the appellant that the decision of the Courts below on both the above points is erroneous.
(3.) WE propose to take up the first point about the plaintiff's right to recover the arrears of increment of pay as claimed by him. It will be noticed from the time scale mentioned above that efficiency bar is reached at the stage of Rs. 75. It has been held by the Courts below upholding the contention of the defendant District Board that in the circumstances of the present case the efficiency bar was not crossed by the plaintiff. Where an efficiency bar is prescribed in a time scale, the increment next above the bar shall not be given without specific sanction of the authority empowered to withhold increments. That is the provision contained in Fundamental Rule 25 which corresponds to Rule 46 of the Bengal Service Rules Part I. The principle contained there will govern the present case. In the present case there was no specific order by the Chairman of the District Board sanctioning the removal of the bar. It is argued however, on behalf of the appellant that though there was no such order in so many words there are circumstances which unmistakably go to show that the District Board authorities treated the case as if the bar had been removed. It is pointed out that on 1st August 1928 the plaintiff wag allowed to draw pay at a rate above RS. 75 and this, it is argued, is consistent with the position that the District Board authorities did in effect waive the bar. In this connection our attention has, however, been drawn to the series of correspondence that passed between the Chairman of the District Board, 24 Parganas, and the Chairman of the Local Board, Basirhat, various office notes regarding fixation of the pay of the appellant, and the series of orders passed by the Chairman of the District Board upon them. On a consideration of all these letters and orders it appears abundantly clear that the appellant drew pay at rates higher than Rs. 75 in spite of the directions of the Chairman of the District Board. There is a letter by the Chairman of the District Board to the Chairman of the Local Board pointing out clearly that the removal of the efficiency bar required the sanction of the Chairman of the District Board and that the appellant's pay should be drawn below the efficiency bar pending the order of the Chairman of the District Board. This position was pointed out again and again but somehow or other the directions of the Chairman of the District Board were not carried out and the appellant continued to draw pay at rates higher than what he was strictly entitled to. There is another circumstance which goes to show that the District Board did not acquiesce in the position that the appellant had been permitted to cross the efficiency bar. It is pertinent in this connection to refer to certain resolutions passed by the District Board. Reference may in this connection be made to the resolution No. 507 passed by the Board on 22nd May 1940 and to resolution No. 530 of the Board passed on 19th June 1940. Resolution No. 507 runs thus : 'Considered the prayer of Babu Bhujagendra Bhusan Banerjee, Clark, on the following points :
(5) Granted pay at the increased rate with all arrear increments due.'
The proceedings of the meeting held on 22nd, May 1940 came up for confirmation on 19th June 1940, and the relevant resolution, viz, resolution -No. 530 passed on that date shows that the word, 'granted' was a mistake for 'refused'. Reading the two resolutions together it is clear enough that the District Board did not consider that the appellant had crossed the efficiency bar and the District Board decided that the plaintiff was not entitled to arrear of increment at the increased rate. Whatever the reason, the District Board, did not choose to claim any refund from the plaintiff. That, however, was in the nature of some indulgence or sympathy shown to the plaintiff, but that circumstance cannot be turned into an argument in support of the plaintiff's claim. In our opinion there is no sufficient reason for us to interfere with the decision of the lower Courts dismissing the claim of the plaintiff for arrear increment.;