JUDGEMENT
-
(1.) The petitioner seeks to have the principal part of an award set aside on the
ground that it is perverse and that the arbitrator has misconducted himself and
the proceedings in awarding an amount despite recording that there was no
evidence to substantiate the extent of loss suffered by the respondent.
Under a purchase order of October 12, 1989 the respondent was required
to take up the job of fabrication, erection and commissioning of two electrostatic
precipitators for the Madhya Pradesh Electricity Board in Korba. It was the
respondent-claimant's case before the arbitrator that despite such contractor
having completed all work, the commissioning could not be done on account of
default on the part of the petitioner herein. The claimant complained in its
statement of claim that it had suffered loss and damage on account of such
inordinate delay and sought an amount of Rs.51 lakh on the ground that the
petitioner herein could not arrange for the commissioning to be completed
despite the claimant being ready and willing to do the same by December, 1992.
The contractor said that it had to wait till the middle of 1994 to complete the
commissioning work and its men and material were uselessly detained at site
when they could have been gainfully engaged elsewhere. The arbitrator
considered such claim under issue no. 3. The arbitrator recorded the basis of the
claim and concluded, on the basis of the material before him, that the head of
claim was justified since the job that remained outstanding was negligible and
was equivalent to five per cent of the work assigned to the contractor. The
arbitrator found that by July, 1992 the contractor had indicated that it would
finish the entirety of the work by December, 1992, but no effective steps were
taken for shutting down the plant to enable the new precipitators to be
commissioned. The award records that the contractor had to wait at the Korba
site needlessly and that it was the petitioner herein who was responsible for the
delay.
(2.) The arbitrator noticed the claim for the 17 months' delay made by the
contractor at Rs.3 lakh per month and the petitioner's contention that the
contractor was not entitled to such amount and the contractor should have taken
appropriate steps for mitigation of damages.
After nearly four pages of discussion on such aspect, the arbitrator held as
follows:
''I am of the view that the claimant has suffered damages. The claimant has
claimed it in particulars specified in the Statement of Claim to justify the
damages of Rs.51 lakhs that it has suffered loss on being detained at
Korba site cannot be doubted. Its claim of Rs.3,00,000/- per month as the
profit per month which it could have earned if it could do similar job is the
claimant's over estimate no doubt. But I am of the view that whether such
contract could have been available to the claimant during the period the
same value was not a certainty. So, it would not be proper to award the
claimant damages for Rs.51 lakhs as claimed by it. However, on
considering the case from all its aspects and regard being had to the fact
that the claimant was a very efficient and competent contractor and even
after the completion of this job the respondent offered it another contract
which the claimant, however, did not undertake, the claim of compensation
made in this arbitration proceeding is genuine as the claimant suffered loss
for being detained for 17 months. However, in the light of the facts and
circumstances of the case I award the claimant Rs.25,00,000/- as
damages.''
(3.) The petitioner argues that the present challenge to such aspect of the
award is not on the basis of any mistake of fact or reasonableness of the reason
in support thereof or of inadequate evidence. The petitioner says that the
assessment of the quantum of damages is based on no evidence at all and is, as
such, perverse. The petitioner concedes that in a matter of such nature there is
an element of guesswork or the application of a thumb rule, but once the
arbitrator recorded that there was no certainty as to whether the contractor
could have obtained alternative work of such value during the period, it was not
open to the arbitrator to conjure up another figure without any material in
support thereof.;
Click here to view full judgement.
Copyright © Regent Computronics Pvt.Ltd.