JUDGEMENT
-
(1.) A work which the Oil and Natural Gas Corporation Ltd. (hereafter ONGC),
respondent 2, entrusted the petitioner s proprietorship firm to execute within 45
days from 10.6.2003 was actually completed on 14.10.2004.
(2.) For delay in complete execution of work, the vigilance cell of ONGC
recommended recovery of Rs.1,70,296/- from the petitioner, inclusive of
Rs.1,31,129/- towards liquidated damages for delayed completion of work and
Rs.39,167/- as penalty for non-deployment of technical persons and non2
maintaining of labour attendance register in terms of the provisions of the
contract.
(3.) However, the final bill for payment raised by the petitioner was allowed and
payment was released without making any deduction towards recovery of
liquidated damages, referred to above. The competent authority of ONGC (not
specified in the counter affidavit of ONGC who he is) had not approved waiver of
liquidated damages. While initiating disciplinary action against the officer
responsible for such lapse, ONGC invoked clause 29 of the contract between the
parties and withheld security deposits of the petitioner in respect of two other
contracts which the petitioner performed successfully aggregating to
Rs.1,31,134/-.;
Click here to view full judgement.
Copyright © Regent Computronics Pvt.Ltd.