JUDGEMENT
-
(1.) This appeal is preferred by the original respondents
against the judgment and order dated July 30, 2003 passed by the
Learned Single Judge in WP No. 11464(w) of 2003. The writ petitioner
moved this court seeking directions against the appellant/respondents to
give electricity connection from the existing 10 KVA Transformer which
may be required for such irrigation purpose primarily on the ground that
the writ petitioner having installed a submersible pump in his agricultural
land in block No. 1041, J.L. 115 Mouza Shitalgram, Block Mongalkot Dist.
Burdwan. It was the case of the writ petitioner that having complied with
all the necessary formalities like an application for getting water available
certificate in his favour in order to install submersible pump for irrigation
and upon maintaining the norms of 200 meters from the nearest irrigation
tubewell/drinking tubewell and submersible pump in his block, the writ
petitioner on 26.6.2002, applied for electric connection but as the
appellant/respondent failed to provide electricity connection he was
required to file an application under Article 226 of the Constitution of
India.
(2.) According to the writ petitioner, the original respondent is bound to give
electricity connection upon receiving the application alongwith necessary
certificate from the writ petitioner. It was stated that prior to the
installation of tubewell for agricultural land there was no other mode of
irrigation and the writ petitioner had to solely depend upon rain water for
irrigation as he being the resident of a remote village in Burdwan.
Farmers in the region have been using the tubewell for the purpose of
irrigation and, therefore, the writ petitioner decided to incur expenditure
approximately Rs. 40,000/- and a 40 feet deep pipe was placed beneath for
installing the submersible pump for irrigation from the tubewell and as
there existed a 10 KVA Transformer, at a short distance, respondents
ought to have supplied electric connection to his submersible pump from
the said Transformer.
The Learned Single Judge found that the petitioner is entitled to take
electricity connection from the 10 KVA Transformer for operating his
submersible pump, and the learned Judge directed the authorities of the
West Bengal State Electricity Board to effect electricity connection to the
submersible pump of the petitioner without any further delay and
positively within a period of 4 weeks from the date of the completion of the
formalities as SWID Certificate is issued by the Authority in favour of the
writ petitioner.
(3.) It further directed to provide electric service connection from the existing
Transformer if the said Transformer can bear the requisite load and if it
does not, appropriate steps should be taken by the authorities for
installation of the new Transformer for the petitioners as well. The learned
Judge also observed that the expenses for the installation of such
Transformer will be borne by the West Bengal State Electricity Board by
placing reliance on the two decisions of this court Kartick Ch. Bose vs. West Bengal State Electricity Board, 2000 AIR(Cal) 218 and B. Chowdhury vs. West Bengal State Electricity Board,2001 1 CalHN 262. The court
having disposed of the writ petition, an application was moved by the
appellant/respondent for recalling the earlier order dated July 30, 2003
and the same also came to be rejected by the order dated November 25,
2000.
At the time when the appeal was listed for hearing none appeared for the
respondent. Therefore, this court proceeded to hear the learned counsel for
the appellant. It is contended by the learned counsel for the appellant that
the Learned Single Judge was pleased to pass the impugned order without
verifying as to whether the writ petitioner has made a proper application
and complied with the necessary formalities for getting electric connection
and without giving opportunity to the appellant board to examine the
feasibility of providing new submersible pumps. It is further contended
that in the event of compliance of formalities by the respondent, the
charges for installation of Transformer will have to be borne by the writ
petitioner. It is submitted that as a matter of policy in case permanent
electric connection is to be provided to the agricultural land, in view of
Policy of 2002 issued by the West Bengal State Electricity Board, electric
connection cannot be provided from the main or transmission network for
various reasons and that the Board cannot be called upon to install 10
KVA Transformer to provide electricity to the petitioner at their cost as the
10 KVA Transformer has to be installed at the cost of the consumer for
providing such electric connection.;
Click here to view full judgement.
Copyright © Regent Computronics Pvt.Ltd.