JUDGEMENT
-
(1.) This appeal is at the instance of the Union of India and is directed against
an order dated 3rd July, 2009 passed by a learned Single Judge of this Court by
which the learned judge dismissed an application under Section 34 of the
Arbitration and Conciliation Act, 1996 (hereinafter referred to as the Act) filed by
the present appellant for setting an Award published on 21st July, 2003 by the
Arbitrator in connection with the dispute that had arisen between the parties in
connection with the Contract No.42M/90-91 dated 14th February, 1990 for
consideration of a Second Class Waiting Hall, Booking Office and other ancillary
works at the Durgapur Station under the Divisional Engineer-II, Asansol, of the
Eastern Railway.
(2.) Pursuant to a tender-notice issued by the Eastern Railway, the
respondent submitted his tender, which was accepted and consequently, a
formal agreement was executed between the parties on 14th December, 1990. The
total value of the contract was Rs.6,23,651.50p and in terms of the contract, the
required work was to be concluded within six months from the date of issue of
the letter of acceptance. The time for completion of the contract-work however,
was, extended at least on 11 occasions and the contract was ultimately
satisfactorily completed after about 43 months.
(3.) According to the appellant, the final bill was prepared and given to it on
8th January, 1996, and the respondent signed the bill and accepted payment.
However, by a letter dated 2nd January, 1997, written through its learned
Advocate, the respondent claimed Rs.17,12,771/- on account of, inter alia,
escalation.;
Click here to view full judgement.
Copyright © Regent Computronics Pvt.Ltd.