JUDGEMENT
-
(1.) The petitioner challenges four several heads of claim that have been
entertained and allowed in the impugned arbitral award. The petitioner says that
the sums awarded on account of overrun charges, crane-hire charges and
interest are in derogation of the agreement between the parties. The petitioner
assails the reduction in the quantum of deduction allowed by the arbitral
tribunal on account of the respondent -claimant failing to complete the painting
work.
(2.) The petitioner obtained an order for setting up some plant or boiler units
and was desirous of engaging a sub-contractor for discharging a part of the work.
Pursuant to a notice inviting tender issued by the petitioner, the respondent
offered to erect, test and commission two 120 MW boilers (Unit II and Unit III) on
behalf of the petitioner. The value of the contract awarded in favour of the
respondent was Rs.6,99,40,000/-. Following disputes and differences having
arisen between the parties, either party nominated its arbitrator and the two
arbitrators chose the third. The arbitral tribunal awarded Rs.69.22 lakh on
various heads and a sum of Rs.25.39 lakh on account of interest.
(3.) In the present proceedings under Section 34 of the Arbitration and
Conciliation Act, 1996, the petitioner says that the arbitral tribunal which
derived its authority under the agreement between the parties could not have
overridden the specific clauses in the contract to give relief to the respondent.
The petitioner says that the arbitral tribunal had no power to consider the claims
on account of overrun charges, crane-hire expenses and interest. On the fourth
count of challenge, the petitioner suggests that the arbitral tribunal misdirected
itself and disallowed the deduction made by the petitioner on irrelevant and
extraneous considerations. In substance, it is the petitioner's case that the
arbitral tribunal failed to decide the reference in accordance with the terms of the
contract, in respect of the matters which have been challenged at the hearing.
The matter was heard at length on February 17, 2010. Upon the
petitioner's submission being concluded, substantial time was wasted by the
respondent on account of the obvious unpreparedness. The matter was
adjourned and costs reserved. Even at the second call in a continuing part-heard
matter, the respondent has not been represented at the hearing on February 18,
2010.;
Click here to view full judgement.
Copyright © Regent Computronics Pvt.Ltd.