JUDGEMENT
-
(1.) The petitioner has applied under Section 11(6) of the Arbitration and
Conciliation Act, 1996 with a request for necessary measures to be taken for
constituting an arbitral tribunal to adjudicate upon the disputes covered by the
arbitration agreement that the petitioner sets up. The respondent has denied the
existence of the arbitration agreement.
(2.) There is no dispute that following a notice inviting tender and the
petitioner's offer thereupon, a work order was issued in favour of the petitioner
for handling and despatch of iron ore fines from Thakurani/Barbil siding to the
ports of Paradip, Haldia and Gopalpur by rail and by road. The work included
port handling, stacking and stevedoring operations. The work order contemplated
a formal agreement being executed. The work order was to remain valid for the
period upto December, 2008 with a provision for extension thereof based on the
performance of the petitioner. The performance was to be reviewed every three
months. Clause 17 of the work order dated January 22, 2008 provided as follows:
A written Agreement will be executed between OSL and OMDC within
7 (seven) days of issuance of the Work Order recording the fact of
conclusion of contract between OSL & OMDC."
(3.) It is not in dispute that a draft agreement was forwarded by the respondent
to the petitioner on January 22, 2008 itself. The same will be evident from a
letter dated February 8, 2008 issued by the respondent, a copy whereof appears
as annexure "R-1" to the respondent's affidavit-in-opposition. Under cover of
such letter, a copy of the draft agreement was forwarded again with a request
that it "may please be finalised immediately for execution in the stamp paper."
The draft agreement contained the following, which the petitioner claims to be an
arbitration clause:
"ARBITRATION: In case of any conflict between the terms and conditions
contained in the contract documents, the provisions
contained herein shall prevail over those contained in the
documents referred above. All disputes and differences of
any kind whatsoever arising out of the Second Part shall
referred to the Sole arbitrator namely of the First Part. On
any reference the Learned Arbitrator will decide the
dispute in accordance with the Arbitration and
Conciliation Act, 1996. The decision and/or award of the
arbitrators will be final and binding upon both the
parties.";
Click here to view full judgement.
Copyright © Regent Computronics Pvt.Ltd.