JUDGEMENT
D.C.Srivastava, J. -
(1.) This is defendant's
second appeal, against the judgment and decree
dated 10th October, 1980 of District Judge,
Saharanpur. The brief .facts are that on 5th
June. 1973 the defendant-appellant entered
into an agreement with the plaintiff-respondent for sale of his three plots No. 757, 787
and 759 for Rs. 7,000/-. The'sale deed was
to be executed within 5 years from the date
of agreement. The plaintiff requested the
defendant several times to execute the sale
deed, but he'avoided. Two notices were sent
on 8th February, 1978 and 18th February,
1978. Through the second notice dated 18th
February, .1978, 3rd March,. 1978 was fixed
as the date for execution of the sale deed, but
the defendant did not respond. The plaintiff
went to the office of Sub-Registrar, got his
presence noted. Thereafter the suit was filed
on 22nd March,. 1978 alleging that the plaintiff was always ready and willing to perform his
part of obligation under the contract and the
defendant refused to execute the sale deed.
(2.) The suit was contested on the ground
that the plaintiff had no means to pay the sale
consideration and was never ready and willing
to perform his part of obligation under the
contract. A notice was given by the defendant
to the plaintiff on 15th March, 1978 in which
30th March, 1978 was fixed as the date for
execution of the sale deed, but the plaintiff did
not respond and did not appear with the
money before the Sub-Registrar.
(3.) The suit was dismissed by the trial
Court observing that the plaintiff was not
ready and willing to perform his part of the
agreement because he had no means to arrange Rs. 7,000/-. An appeal was filed, which
was allowed, hence this second appeal. Only
two substantial questions of law arose in this
second appeal. The first is whether the suit
was premature. Learned Counsel for the appellant on this point argued that since the
agreement was executed on 5th June, 1973
and the period stipulated was 5 years, the suit
could not be filed before 5th June, 1978.
Reliance was placed upon the pronouncement in Harihar Singh v. Udaibir Singh,
wherein it was laid down that the cause of
action in such cases of specific performance
of contract arises only after the time for
performance of contract expires. It was held
that since the suit was filed before the expiry
of the prescribed time, the suit was premature and was liable to be dismissed. The
first Appellate Court has not answered this
plea of the defendant-appellant and has observed that this
may not be considered material since the time limit did expire after the suit
had been brought and there can be no legitimate bar to the Court taking notice of this
subsequent fact also.. Thus the first Appellate
Court did not answer this question. For answering this question, agreement has to be
referred and it is to be seen whether cause of
action, on the facts of the case, accrued after
the expiry of the period mentioned in the
agreement or upon the defendant's refusal
and avoidance to execute the sale deed.;
Click here to view full judgement.
Copyright © Regent Computronics Pvt.Ltd.