JAGJEET SINGH LYALLPURI Vs. UNITOP APARTMENTS & BUILDERS LTD.
LAWS(SC)-2019-12-4
SUPREME COURT OF INDIA
Decided on December 03,2019

Jagjeet Singh Lyallpuri Appellant
VERSUS
Unitop Apartments And Builders Ltd. Respondents

JUDGEMENT

A.S.BOPANNA,J. - (1.) The appellants are before this Court assailing the order dated 31.07.2015 passed by the High Court of Punjab and Haryana at Chandigarh in FAO No. 5704 of 2012 (O&M). Through the said order, the High Court has remanded the matter to the sole Arbitrator Mr. Justice Kuldip Singh, retired Judge, Supreme Court of India for providing opportunity of leading evidence to both the parties and also grant opportunity to crossexamine the witnesses and thereafter decide each and every claim and counter claim separately on merits. The said order is passed in an appeal filed by the respondent herein under Section 37 of the Arbitration and Conciliation Act, 1996 ('Act 1996' for short). The appellant herein who was the respondent in the said appeal is therefore before this Court claiming to be aggrieved by the said order.
(2.) The brief facts leading to the present situation is that the appellants herein are joint owners of the land measuring 14 Kanals and 3 Marlas (8560 Sq. yards) situate at village Sunet, Tehsil and District Ludhiana, State of Punjab. The respondent company through its representatives claiming to be wellversed with construction and development of properties approached the appellants for joint venture in constructing a residentialcum commercial complex on the subject land. Accordingly, an agreement dated 14.12.1996 was entered into and among other terms agreed therein, the respondent had undertaken to complete the construction of the building consisting of at least six floors within three years from the date of obtaining the sanctioned plan from the Ludhiana Municipal Corporation. The project was required to be funded by the respondent and a sum of Rs. 45,00,000/ (Rupees Forty Five Lakhs only) was to be deposited with the appellant as a guarantee for completion of the project. In that view, the appellants were expected to retain the same if the building is not completed within the period of three years. The sale proceeds from the constructed building was to be shared in the ratio of 48:52 % between the appellants and the respondent.
(3.) Pursuant to such agreement the respondent secured the sanction of the building plan from the Municipal Corporation on 04.07.1997. The period of three years was to be computed from that point as per the agreement. Hence the construction ought to have been completed by 03.07.2000. According to the appellant, the respondent though commenced the construction during August, 1997, the activity was undertaken until 31.03.1999 and the project was abandoned by them thereafter. Since the construction was not completed by 03.07.2000 and no further progress was made despite the appellant having waited beyond the said period, the appellants got issued a legal notice dated 01.11.2001 and terminated the agreement dated 14.12.1996. The respondent though issued reply dated 28.11.2001 did not proceed further to make progress in the construction.;


Click here to view full judgement.
Copyright © Regent Computronics Pvt.Ltd.