JUDGEMENT
A.S.BOPANNA,J. -
(1.) The appellants are before this Court assailing the order dated 31.07.2015 passed by the High Court of Punjab
and Haryana at Chandigarh in FAO No. 5704 of 2012
(O&M). Through the said order, the High Court has remanded the matter to the sole Arbitrator Mr. Justice
Kuldip Singh, retired Judge, Supreme Court of India for
providing opportunity of leading evidence to both the
parties and also grant opportunity to crossexamine the
witnesses and thereafter decide each and every claim and
counter claim separately on merits. The said order is
passed in an appeal filed by the respondent herein under
Section 37 of the Arbitration and Conciliation Act, 1996
('Act 1996' for short). The appellant herein who was the
respondent in the said appeal is therefore before this Court
claiming to be aggrieved by the said order.
(2.) The brief facts leading to the present situation is that the appellants herein are joint owners of the land
measuring 14 Kanals and 3 Marlas (8560 Sq. yards) situate
at village Sunet, Tehsil and District Ludhiana, State of
Punjab. The respondent company through its
representatives claiming to be wellversed with construction
and development of properties approached the appellants
for joint venture in constructing a residentialcum
commercial complex on the subject land. Accordingly, an
agreement dated 14.12.1996 was entered into and among
other terms agreed therein, the respondent had undertaken
to complete the construction of the building consisting of at
least six floors within three years from the date of obtaining
the sanctioned plan from the Ludhiana Municipal
Corporation. The project was required to be funded by the
respondent and a sum of Rs. 45,00,000/ (Rupees Forty
Five Lakhs only) was to be deposited with the appellant as
a guarantee for completion of the project. In that view, the
appellants were expected to retain the same if the building
is not completed within the period of three years. The sale
proceeds from the constructed building was to be shared in
the ratio of 48:52 % between the appellants and the
respondent.
(3.) Pursuant to such agreement the respondent secured the sanction of the building plan from the Municipal
Corporation on 04.07.1997. The period of three years was
to be computed from that point as per the agreement.
Hence the construction ought to have been completed by
03.07.2000. According to the appellant, the respondent though commenced the construction during August, 1997,
the activity was undertaken until 31.03.1999 and the
project was abandoned by them thereafter. Since the
construction was not completed by 03.07.2000 and no
further progress was made despite the appellant having
waited beyond the said period, the appellants got issued a
legal notice dated 01.11.2001 and terminated the
agreement dated 14.12.1996. The respondent though
issued reply dated 28.11.2001 did not proceed further to
make progress in the construction.;
Click here to view full judgement.
Copyright © Regent Computronics Pvt.Ltd.