MAJOR RETD INDER SINGH REKHI Vs. DELHI DEVELOPMENT AUTHORITY
LAWS(SC)-1988-3-23
SUPREME COURT OF INDIA (FROM: DELHI)
Decided on March 24,1988

INDER SINGH REKHI Appellant
VERSUS
DELHI DEVELOPMENT AUTHORITY Respondents

JUDGEMENT

SABYASACHI MUKHARJI - (1.) SPECIAL Leave granted.
(2.) THE Delhi Development Authority vide its letter dated 5/10/1976 accepted the tender of the appellant for construction of 240 Janta Houses at the estimated cost of Rs. 24,49,262.00. THE work was to commence on 15/10/1976 and was required to be completed by 14/07/1977. By a subsequent extension of time the work was finally completed on 2/04/1980 and the houses so constructed have been allotted to several people. Between Feb. 1983 to Dec. 1985 the appellant sent several letters to the respondent requesting them to finalise the bills. It appears, however, that the first of such letters was written on 28th Feb. 1983. THEreafter the appellant wrote several letters and finally on 4th Sept. 1985 to the respondent to finalise the bills and ultimately served the notice through his counsel requesting it to release the security of Rs. one lakh and refer the dispute to arbitration. THE respondent failed to do so. In Jan. 1986 the appellant filed an application under S. 20 of the ARBITRATION AND CONCILIATION ACT, 1940 (hereinafter called 'the Act') seeking a direction from the Court that the respondent be directed to file the arbitration agreement in the Court and the dispute be referred to the arbitration. THE learned single Judge of the High Court of Delhi dismissed the application as barred by time. THEre was an appeal to the Division Bench of the High Court of Delhi. THE Division Bench upheld the decision of the learned single Judge. Hence this appeal to this Court. The question is, whether the High Court was right in upholding that the application under S. 20 of the Act was barred by limitation. In view of the decision of this Court in Kerala State Electricity Board, Trivendrum v. T.P.K.K. Amsom (1977) 1 SCR 996: (AIR 1977 SC 282), it is now well-settled that Art. 137 of the Limitation Act, 1963 would apply to any petition or application filed in a Civil Court. Sub-sec. (1) of S. 20 of the Act provides as follows : "Application to file in Court arbitration agreement : - Where any persons have entered into an arbitration agreement before the institution of any suit with respect to the subject-matter of the agreement or any part of it, and where a defence has arisen to which the agreement applies, they or any of them, instead of proceeding under Chapter II, may apply to a court having jurisdiction in the matter to which the agreement relates, that the agreement be filed in Court."
(3.) THEREFORE, in order to be entitled to order of reference under S. 20, it is necessary that there should be an arbitration agreement and secondly, difference must arise to which this agreement applied. In this case, there is no dispute that there was an arbitration agreement. There has been an assertion of claim by the appellant and silence as well as refusal in respect of the same by respondent. THEREFORE, a dispute has arisen regarding non payment of the alleged dues of the appellant. The question is for the present case when did such dispute arise. The High Court proceeded on the basis that the work was completed in 1980 and, therefore, the appellant became entitled to the payment from that date and the cause of action under Art. 137 arose from that date. But in order to be entitled to ask for a reference under S. 20 of the Act there must not only be an entitlement to money but there must be a difference or a dispute must arise. It is true that on completion of the work a right to get payment would normally arise but where the final bills as in this case have not been prepared as appears from the record and when the assertion of the claim was made on 28th Feb. 1983 and there was non-payment, the cause of action arose from that date, that is to say, 28th of Feb. 1983. It is also true that a party cannot postpone the accrual of cause of action by writing reminders or sending reminders but where the bill had not been finally prepared, the claim made by a claimant is the accrual of the cause of action. A dispute arises where there is a claim and a denial and repudiation of the claim. The existence of dispute is essential for appointment of an arbitrator under S. 8 or a reference under S. 20 of the Act. See Law of Arbitration by R.S. Bachawat, 1st Edition, page 354. There should be dispute and there can only be a dispute when a claim is asserted by one party and denied by the other on whatever grounds. Mere failure or inaction to pay does not lead to the inference of the existence of dispute. Dispute entails a positive element and assertion in denying, not merely inaction to accede to a claim or a request. When in a particular case a dispute has arisen or not has to be found out from, the facts and circumstances of the case.;


Click here to view full judgement.
Copyright © Regent Computronics Pvt.Ltd.