JUDGEMENT
Sabyasachi Mukharji, J. -
(1.) This appeal by special leave is from the judgment and order of the Full Bench of the Madhya Pradesh High Court, dated 8th December, 1986.
(2.) The writ petition in question out of which this judgment arose had been referred to the Full Bench by the Division Bench on the question whether the petitioner-appellant could be said to have effected entry of the goods in the local area and thereby made it liable for payment of entry tax under S. 3 of the M.P. Sthaniya Kshetra Me Mal Ke Pravesh Par Kar Adhiniyam, 1976 (hereinafter called 'the Act'). There was conflict between the Division Benches of the Madhya Pradesh High Court and as a result the matter was referred to the Full Bench. In order to appreciate the controversy and the question, it is necessary to state a few facts.
(3.) The appellant-company is a building contractor at Rajnandgaon in Madhya Pradesh and is registered as a dealer under the Madhya Pradesh General Sales Tax Act. The appellant's tender for construction of foodgrains godown and ancillary buildings at Rajnandgaon was accepted by the Central Public Works Department. It was an item rate tender. In the tender so submitted by the appellant, the prices of the materials to be used for the construction including cost of iron, steel and cement were included. The PWD, however, had agreed to supply from its stores the said iron, steel and cement for the construction work and to deduct the prices of materials so supplied and consumed in the construction from the final bill of the appellant. Clause (10) of the contract is relevant and was as follows:
"Clause 10.- If the specification or Schedule of terms provides for the use of any special description of materials to be supplied from Engineer-in-charge's Stores, or if it is required that the Contractor shall use certain stores to be provided by the Engineer-incharge as shown in the Schedule of materials hereto annexed, the contractor shall be bound to procure and shall be supplied such material and stores as are from time to time required to be used by him for the purposes of the contract only, and the value of the full quantity of materials and stores to supply at the rates specified- in the said Schedule of materials may be set off or deducted from any sums then due or thereafter to become due to the contractor under the contract or otherwise, or against or from the security deposit, or the proceeds or sale thereof if the same is held in Government securities, the same or a sufficient portion thereof being in this case sold for the purpose. All materials so supplied to the contractor shall remain the absolute property of Government and shall not be removed on any account from the site of the work, and shall be at all times open to inspection by the Engineer- in-charge. Any such materials remaining unused and in perfectly good condition at the time of the completion or determination of the contract shall be returned to the Engineer-in-charge at a place directed by him, if by a notice in writing under his hand he shall so require; but the contractor shall not be, entitled to return any such materials unless with such consent and shall have no claim for compensation on account of any such materials so supplied to him as aforesaid not being used by him or for any wastage in or damage to any such materials. Provided that the contractor shall in no case be entitled to any compensation or damages on account of any delay in supply or non-supply thereof all or any such materials and stores. Provided further that the contractor shall be bound to execute the en tire work if the materials are supplied by the Government within the scheduled time for completion of the work plus 50 per cent thereof (scheduled time plus 6 months if the time of completion of the work exceeds (12 months) but if a part only of the materials has been supplied within the aforesaid period, then the contractor shall be bound to do so much of the work as may be possible with the materials and stores supplied in the aforesaid period. For the completion of the rest of the work, the contractor shall be entitled to such extension of time as may be determined by the Engineer-in-charge whose decision in this regard shall be final.";
Click here to view full judgement.
Copyright © Regent Computronics Pvt.Ltd.