M/S INDIAN FARMERS FERTILIZER CO-OPERATIVE LIMITED Vs. M/S BHADRA PRODUCTS
LAWS(SC)-2018-1-29
SUPREME COURT OF INDIA
Decided on January 23,2018

M/S Indian Farmers Fertilizer Co-Operative Limited Appellant
VERSUS
M/S Bhadra Products Respondents

JUDGEMENT

R.F.NARIMAN,J. - (1.) Leave granted.
(2.) An interesting question arises as to whether an award delivered by an Arbitrator, which decides the issue of limitation, can be said to be an interim award, and whether such interim award can then be set aside under Section 34 of the Arbitration and Conciliation Act , 1996 (hereinafter referred to as "the Act"). The brief facts necessary to dispose of the present appeal are as follows.
(3.) The appellant before us issued a tender enquiry to 19 parties, including the respondent, for supply of Defoamers. The respondent submitted its bid, pursuant to which a Letter of Intent dated 2nd November, 2006 was issued to the respondent for supply of 800 Metric Tonnes of Defoamers to be used for production of 3,08,880 Metric Tonnes of P2O5. By 11th April, 2007, the respondent had supplied 800 Metric Tonnes of Defoamers, however, they could not achieve the targeted production by the end of 1st November, 2007, which was the validity of the supply period. After considerable delay, on 6 th June, 2011, the respondent issued a legal notice demanding payment of Rs.6,35,74,245/- on 27th September, 2012. The appellant made it clear that there was nothing due and payable to the respondent. Since disputes arose between the parties, on 1st October, 2014 the respondent invoked arbitration, and on 25th January, 2015, Justice Deepak Verma, a retired Judge of the Supreme Court, was appointed as the sole arbitrator. On 3rd March, 2015, issues were framed. On 23 rd July, 2015, the learned Arbitrator thought it fit to take up the issue of limitation first, inasmuch as the counsel appearing for both the parties submitted that this issue could be decided on the basis of documentary evidence alone. This issue was then decided in favour of the claimant stating that their claims had not become time barred. A petition filed under Section 34 of the Act challenged the aforesaid award, styling it as the 'First Partial Award'. On 8th October, 2015, the District Judge, Jagatsinghpur, dismissed the Section 34 Petition stating that the aforesaid award could not be said to be an interim award and that, therefore, the Court lacked jurisdiction to proceed further under Section 34 of the Act. The appeal to the High Court of Orissa was dismissed by the impugned order dated 30th June, 2017, reiterating the reasoning of the learned District Judge.;


Click here to view full judgement.
Copyright © Regent Computronics Pvt.Ltd.