JUDGEMENT
-
(1.) The three awards were passed on 25.11.2007, 14.2.2008 and 29.3.2009 by the learned Arbitrator in favour of the petitioner.
(2.) The petitioner had filed a claim against the erstwhile Jharkhand State Electricity Board (for short, the 'Board') in
respect of allocation project contracts dated 10.2.2005 and
22.4.2006.
(3.) Purporting to challenge these awards, the respondents (erstwhile Board) filed an application under section 34 of the
Arbitration and Conciliation Act, 1996 (for short, the 'Act').
This application along with the applications for condonation
of delay was filed on 04.11.2010. Admittedly, the application
under section 34 of the Act was delayed. As a matter of fact,
the delay is of various periods with respect to the chronology
of the awards. The application/s against the first award was
delayed by 1005 days, against the second award by 610 days and
against the third award by 107 days. These applications were
allowed by the Sub-Judge I, Ranchi. The High Court upheld
the order of learned Sub-Judge I, Ranchi, condoning the delay
in filing application under section 34 of the Act. The review
petition filed by the petitioner was also rejected. Hence,
these special leave petitions.;
Click here to view full judgement.
Copyright © Regent Computronics Pvt.Ltd.