JUDGEMENT
A.K.MATHUR, J. -
(1.) THIS appeal is directed against the order passed by the Delhi High Court
dated 24.5.2005 challenging the partial award given by the International
Chamber of Commerce, Arbitration Tribunal on 31.7.2002.
(2.) BRIEF facts which are necessary for disposal of this appeal are that on 6.12.1999 the parties entered into a contract for setting up of 817 MW
Gas Based Combined Cycle Power Project at Dadri, UP. at a price of DEM
324,405,000 equivalent to Rs. 2,190,000,000/- (Rupees two thousand one hundred ninety million). At the request of the respondent-Siemens
Atkeingesellschaft (hereinafter to be referred to as ï¿ 1/2SAGï¿ 1/2) three
separate contracts were entered into with cross-fall breach clause. One
contract was with respondent-SAG known as ï¿ 1/2:First Contractï¿ 1/2 and the other
with its associates, namely Bharat Heavy Electricals Limited (BHEL), New
Delhi and the third with Siemens Limited, Bombay. Consfderable delay
occurred in execution of the contract which was mostly attributable to
the appellant-National Thermal Power Corporation (hereinafter to be
referred to as ï¿ 1/2NTPCï¿ 1/2), due to delay in opening of Letters of Credit in
favour of the respondent-SAG and in obtaining import licences for various
equipments from Statutory Authorities. Respondent raised several claims
against the appellant-NTPC for losses resulting from delay. On the other
hand, the appellant was also facing acute ï¿ 1/2difficulty in getting the
critical components and spare parts and tools from the respondent. In
order to sort out the said disputes, a high-powered meeting of the
parties was held on 6th/7th April, 2002 in which several decisions were
taken. One of the decisions taken in the meeting was that the respondent
was to supply the critical components and spare parts etc. to the
appellant-NTPC on its part and on the other hand the appellant-NTPC
agreed to look into the claim raised by the respondent-SAG with more
positive approach in view of the fact that there was delay in arranging
import licences and opening of Letter of Credit by the appellant-NTPC. In
pursuance to the decision, the respondent-SAG supplied the critical
components etc. but the appellant-NTPC did not favourably consider the
claim of the respondent-SAG for damages on account of the aforesaid
delay. Subsequently, the respondent-SAG made a reference to ICC Court of
Arbitration, Paris for settlement of their disputes/claimï¿ 1/2 to
compensation on account of delay in terms of Clause 27 of the Contract.
The ICC International Court of Arbitration registered the reference as
Case No. 11728/ACS and on 5th May, 2002 issued terms of reference. The
ICC International Court of Arbitration was comprised of three
Arbitrators, namely Mr. Arthur Marriott QC, Chairman and Mr. Justice R.S.
Pathak and M r. Justice A.M. Ahmadi, two former Chief Justices of the
Supreme Court of India. While the claim of the respondent-SAG related
largely to compensation on account of delay on the part of the
appellant-NTPC in procuring the import licences and belated opening of
the Letter of Credit in favour of the respondent, the appellant-NTPC
besides filing their defence to the said claims also filed several
counter claims on various counts amounting to hundreds of crores of
rupees against the respondent-SAG. The respondent-SAG resisted the said
counter claims of the appellant-NTPC inter alia on the grounds that the
counter claims were not arbitrable because the claims had been waived
and/or abandoned and/or discharged and/or satisfied or compromised and
the appellant had failed to fulfil the condition precedent to arbitration
specified in Clauses 26 & 27 of the General Conditions of Contract.
Number of issues were framed and the Tribunal after considering the
submissions of the parties, gave a partial award on 31.7.2002 and held
that the claim of the respondent-SAG was maintainable and was not barred
by limitation while the counter claims of the appellant-NTPC was not
admissible because the same were caught by the agreement contained in the
minutes of meeting (MoM) dated 6th/7th April, 2000. Aggrieved against
this partial award so far as it nonsuited the appellant-NTPC in respect
of their counter claims, the appellant-NTPC directly approached the High
Court by filing an appeal.
The preliminary objection which was raised before the High Court was whether the appeal filed against the partial award of the ICC
International Court of Arbitration was maintainable or not. Learned
Single Judge of the High Court after elaborate discussions on the
subject, took the view that the appeal under Section 37(2) (a) of the
Arbitration & Conciliation Act, 1996 (hereinafter to be referred to as
ï¿ 1/2the Actï¿ 1/2) was not maintainable. It was observed by the learned Single
Judge as follows:
This Court on a thorough examination of the material obtaining on record, more particularly on a conjoint reading of the pleadings of the parties filed before the Arbitral Tribunal, the Terms of Reference framed by the International Chamber of Commerce, the written submissions filed by the parties before the Arbitral Tribunal prior and after the closure of the hearing, the tenor of the reasoning and finding recorded by the Arbitral Tribunal in its dispensation titled as ï¿ 1/2Partial Final Awardï¿ 1/2 and on a tr ue construction and scope of the provisions of Section 16 and Section 37 of the Act, is clearly of the view that the impugned dispensation dated 31.7.2002 rendered by the Arbitral Tribunal cannot by any stretch be said to be an order passed by the Tribunal either under the provisions of Section 16(2) or Section 16(3) of the Act and in any case deciding the question of jurisdiction in the negative which will fall within the ambit of appelable orders within the meaning of Section 37(2)(a) of the Act. In the opinion of this Court, the impugned partial Award is nothing but an Award of interim Award deciding the counter claims of the NTPC finally on merits. This Court, therefore, must hold that the present appeal filed by the NTPC against such a Partial Award under the provisions of Section 37(2)(a) of the Act is misconceived and is not maintainable.
Aggrieved against this order, the present appeal has been filed by the
appellant-NTPC.
(3.) WE have heard learned counsel for the parties and perused the records. The question before us in the present appeal is whether the view taken by
learned Single Judge of the High Court that the appeal under Section 37
of the Act is maintainable against the interim award or not. Learned
counsel for the appellant took us through all the details of the
pleadings and tried to persuade us that the question of jurisdiction and
limitation is involved, therefore, the appeal is maintainable under
Section 37 of the Act.;
Click here to view full judgement.
Copyright © Regent Computronics Pvt.Ltd.