JUDGEMENT
-
(1.) Leave granted. Heard learned counsel for the parties.
The Ahmedabad Municipal Corporation (AMC for short) decided to
construct a bridge across the river Sabarmati. In that behalf AMC sought financial
contribution from Ahmedabad Electricity Company (AEC), Oil & Natural Gas
Commission (ONGC) and Gujarat State Road Transport Corporation (GSRTC). As
the cost was estimated to be Rs.11 crores, it was agreed that AMC, AEC,
ONGC and GSRTC will bear the cost in the ratio of Rs.4 crores, Rs.1 crore, Rs.2
crores and Rs.4 crores respectively. According to AMC, it was further agreed that in
the event of the cost exceeding Rs.11 crores, the excess to the extent of Rs.1 crore
would be borne by ONGC and AEC in the proportion of 2:1. AMC appointed AEC
as its agent for construction of the bridge. The work was entrusted to the appellant
for execution. The cost of construction turned out to be Rs.11,38,06,000/-. It is stated
that the additional cost of Rs.38,06,000/- was borne by ONGC and AEC in the ratio
of 2:1 as per the earlier understanding.
(2.) Thereafter, the contractor raised certain disputes in regard to its claims
aggregating to Rs.1,33,36,200/-. The said disputes were referred to arbitration. AMC,
AEC, ONGC and GSRTC were made respondents in the arbitration proceedings.
The Arbitrator by award dated 15.6.1999, awarded a sum of Rs.20,14,860/- to the
appellant contractor and directed that AMC and AEC shall pay the said amount
with interest at the rate of 12% per annum from the date of award till date of
realisation (in the manner set out in para 24 of the award). Feeling aggrieved by the
award, AEC filed an application before the City Civil Court, Ahmedabad under
Section 34 of the Arbitration and Conciliation Act, 1996 ('Act' for short). The City
Civil Court by its judgment dated 15.9.2003 upheld the award directing the payment
of Rs.20,14,860/- with interest at the rate of 12% per annum to the contractor.
However, the trial court held that AMC was not liable to pay any amount. It held that
AEC was liable to pay one-third of the award amount and ONGC was liable to pay
two-third of the award amount. Consequently it directed AEC to pay RS.6,71,620/-
plus interest and ONGC to pay Rs.13,43,240/- plus interest to the contractor.
(3.) Feeling aggrieved by the modification of the award, ONGC filed an appeal
before the High Court of Gujarat. ONGC contended that having regard to the scope
of Section 34 of the Act, the Court ought not to have shifted the liability from AMC
to ONGC. On the other hand AMC supported the order of the trial court. The High
Court by its judgment dated 27.9.2005 allowed the appeal. It held that the ONGC
could not have been made liable to pay Rs.13,43,240/- with interest in modification of
the award of the Arbitrator. The High Court was of the view that having regard to
the nature of jurisdiction exercised under Section 34 of the Act, and as the provisions
of Section 96 and Order 41 Rule 33 of CPC were inapplicable, the trial court could
not have shifted the liability from AMC to ONGC. Therefore, the High Court set
aside the decision of the trial court to the extent it held that ONGC was liable to pay
Rs.13,43,240/- with interest.;
Click here to view full judgement.
Copyright © Regent Computronics Pvt.Ltd.