JUDGEMENT
-
(1.) Leave granted. Heard both counsel. The question involved in
this appeal is whether a dispute raised by an insured, after giving a
full and final discharge voucher to the insurer, can be referred to
arbitration.
(2.) The respondent (Insured) obtained a standard Fire and Special
Perils (with a floater) Policy from the appellant ('Insurer') to cover its
goods in its godowns situated at Surat for the period 4.8.2003 to
3.8.2004. The sum insured was Rs. Three crores, subsequently
increased to Rs. Six crores. On 27.5.2004 the respondent requested
the insurer to increase the sum insured by another Rs. six crores for a
period of two months. Accordingly, the appellant issued an additional
endorsement increasing the sum insured by another Rupees six crores,
in all Rupees twelve crores. The respondent alleges that the additional
endorsement cover issued by the appellant was for 69 days, that is
from 27.5.2004 to 3.8.2004. The appellant alleges that the additional
endorsement cover was for a period of 60 days from 27.5.2004 to
26.7.2004. (Note: The appellant claims that during subsequent
investigations, it came to light that its AAO (Dilip Godbole) had
delivered to the respondent, a computer generated Additional
Endorsement (unauthorisedly altered by hand) showing the period of
additional cover as 69 days up to 3.8.2004, and departmental
proceedings have been initiated against the said officer).
(3.) On 5.8.2004, the respondent reported loss/damage to their
stocks on account of heavy rains and flooding which took place on
2/3.8.2004 and made a claim in that behalf. The surveyor submitted a
preliminary report dated 14.8.2004 followed by a final survey report
dated 6.12.2004 according to which the net assessed loss (payable to
respondent) was Rs.3,18,26,025/-. The said sum was arrived at on the
basis that the sum insured was Rs.12 crores, the actual value of stocks
in the godowns at risk was Rs.8,15,99,149/-, value of damaged goods
was Rs.5,22,81,001/-, and the recoverable salvage value was
Rs.1,87,79,922/-. The appellant informed the surveyor by letter dated
1.3.2005 that there was an error in the net assessed loss arrived at by
the surveyor as it assumed the sum insured as Rs.12 crores up to
3.8.2004 whereas the sum insured was only Rs.6 crores after
26.7.2004 till 3.8.2004, and therefore instructed the surveyor to
prepare the final report regarding net assessed loss by taking the sum
insured as only Rupees six crores. The surveyor therefore gave an
addendum to the final survey report on 22.3.2005 reassessing the net
loss by taking the sum insured as only Rupees six crores. The value of
goods at risk, the value of damaged goods and the value of
recoverable salvage remained unaltered. By modifying the percentage
of insurance at 75.53%, the 'Net Assessed Loss' was re-worked as
Rs.2,34,01,740/-. The respondent protested against the loss being
assessed by taking the sum insured as only Rupees six crores. The
claim and the dispute were pending consideration for a considerable
time.;
Click here to view full judgement.
Copyright © Regent Computronics Pvt.Ltd.