JUDGEMENT
-
(1.) Leave granted.
(2.) The respondent, Pawanhans Helicopters Pvt. Ltd.
(hereinafter called "Pawanhans") a Government of India
undertaking, floated two tenders for allocation of work for
construction of a compound wall and a bridge over a nala.
Pursuant to the aforesaid information, several tenders were
received and the tenders of the appellant (hereinafter called
the "contractor") were ultimately accepted. Pursuant to the
aforesaid, two formal agreements providing for the terms and
conditions of the contract in the shape of general conditions
of the contract and special conditions of the contract
governing the execution of work were duly signed on 12th
October 1999. As per the contract the work was required to
be completed within four months. It appears that on account
of some delay which was attributable to Pawanhans, the work
did not proceed as per schedule and the contractor
accordingly informed Pawanhans by letters dated 15th
February 1990, 23rd February 1990, 24th March 1990, 26th
June 1990 and 6th July 1990 that the work was getting
delayed as the requisite facilities for its completion had not
been provided and highlighting several factors attributable to
it had supervened which had led to the delay. The contractor
also in the meanwhile vide letters dated 27th July 1990 and 6th
August 1990 requested the respondent to release the
outstanding bills against the work already completed and also
requested for the "Virtual Completion Certificate" vide letter
dated 25th August 1990. As some work on the compound wall
still remained to be completed, the contractor agreed to take
up this assignment subject to waiver of the discount of 8.2%
which was to be given to Pawanhans till then and the
completed works were duly handed over to Pawanhans on the
12th November 1990. The contractor had also submitted a bill
dated 23rd June 1991 and it was conveyed to Pawanhans that
it expected compensation on account of the variation in the
terms of the contract. Pawanhans thereupon advised the
contractor to submit a final bill which too was submitted. The
bill was verified by Pawanhans and referred to the contractor
yet again with objections. The contractor vide letter dated 21st
November 1991 disputed the verification as being without any
foundation and also reserved its right to seek arbitration.
After a protracted correspondence, Pawanhans vide letter of
9th December 1991 advised the contractor to submit a "No
Claim Certificate" as a pre-condition for the release of the
balance payment. The contractor wrote to Pawanhans that it
was in dire need of finances and was being subjected to
duress but nevertheless submitted a "No Dues Certificate"
dated 17th February 1992 once again specifically highlighting
that the same was being issued under duress. It appears that
despite the issuance of the aforesaid certificate, Pawanhans
still did not release the payment on which the contractor wrote
another letter dated 5th May 1992 and several letters
thereafter but again to no effect, and on the contrary received
a letter dated 8th June 1992 from Pawanhans asking for a "No
Dues Certificate" as per the enclosed specimen without
attaching any condition to the same. The contractor, now in a
desperate situation, submitted yet another "No Claim
Certificate" dated 18th June 1992 as per directions. After
receiving the aforesaid document, Pawanhans in its letter
dated 9th February 1993 informed the contractor that a period
of two months would be required for the scrutiny of its bills
and vide letter dated 21st May 1993 also intimated that the
bills had been submitted for verification by the
Architect/Engineer as per the terms of the contract and that
in case it was willing to defray the payment, the matter could
be referred to arbitration. The contractor finally received a
communication dated 8th June 1993 pointing out that as all
payments due under the contract had been made and as a "No
Dues Certificate" had been furnished, no further amount was
due. The contractor accordingly served a notice dated 28th
June 1993 on Pawanhans invoking the clause relating to
arbitration. The matter was referred to arbitration by two
registered Architects as per the clause. The contractor
submitted its statement of claim for the outstanding amount
plus compensation and damages on 6th August 1994. The
arbitrators passed two awards on 31st December 1996, one
with respect to the contract for the compound wall and the
second for the construction of the bridge awarding certain
amounts to the contractor. Aggrieved by the awards,
Pawanhans filed two separate petitions under sections 30 and
33 of the Arbitration Act, 1940 before the Bombay High Court
for a direction that the awards be set aside. The learned
Single Judge in his judgment and order dated 9th December
1998 held that clauses 18 and 34 of the contract when read
together, provided for the payment of escalation charges as
the work had not been completed within four months on
account of the fault on the part of the respondent and that the
said clauses did not prohibit such a payment, more
particularly as time was the essence of the contract and as the
contract was not on a fixed price, the prohibition of escalation
was if at all to be read during the period of contract only. The
learned Single Judge also repelled the arguments of the
respondent that after having submitted the final bill on 25th
October 1991, it was not open to the appellant herein to
submit a second final bill on 2nd February 1993 by observing
that the payment received on the 4th July 1993 as a
consequence of the bills submitted on 25th October 1991, was
under duress and it is on that account that the appellant had
given the aforesaid certificate. Some objections raised by the
respondent herein were however accepted by the learned
Single Judge and the award was accordingly modified and it is
the admitted case that the aforesaid modification has been
accepted and was not challenged before the Division Bench by
the contractor.
2. Two appeals were thereafter filed by Pawanhans before
the Division Bench of the Bombay High Court. The
Division Bench vide its order dated 7th June 2007
allowed the appeals and set aside the order dated 9th
December 1998 of the learned Single Judge as also the
two awards dated 31st December 1996 by highlighting as
a preface that it could not be disputed that the scope for
interference by the court under section 30 or 33 of the
Arbitration Act was limited as the court could not sit as a
court of appeal on the decisions arrived at by the
arbitrator. The Court then applied the aforesaid
principle to the facts of the case and relied on clauses 18
and 34 ibid observed that a plain reading of the said
clauses did not visualize any claim for escalation or
reduction towards the cost of the work and again
reiterated that clause 34 of the agreement prohibited the
contractor from claiming any extra amount on account of
fluctuation of price. The Court further observed,
somewhat in contradiction, that a remedy towards the
escalation of price had been provided by clause 43 of the
contract and clause 43-1(E) specifically provided, the
procedure whereby such a claim could be made and as
the procedure prescribed by the clause had not been
adopted, it was not open to the contractor to contend
before the arbitrator that it was entitled to some
payments on account of price escalation. The Court
finally concluded that:
"Once it is clear that the respondents are
not entitled to claim escalation charges
and the entire dispute, which is the
subject matter of the appeals being
related to the escalation charges, the
impugned orders, to the extent they
confirm the award in relation to the
escalation charges, are liable to be set
aside and the petitions filed by the
appellants challenging the awards in
relation to the grant of the escalation
charges are liable to be allowed to that
extent. Consequently, the claims for
interest on the amount of damages
awarded towards the escalation are also
liable to be set aside."
(3.) The Division Bench then examined the issues raised by
the contractor as to whether that "No Due Certificate" had
been given under duress and held that there was no evidence
to show that the said certificate had been given under duress
or coercion and as the certificate itself provided a clearance of
no dues, the contractor could not now turn and say that any
further payment was still due on account of the second final
bill. The Division Bench accordingly allowed the appeal. The
matter is before us in these circumstances.;
Click here to view full judgement.
Copyright © Regent Computronics Pvt.Ltd.