JUDGEMENT
A.K.SIKRI,J. -
(1.) Though this case has a chequered history, only those facts which are very material are taken note of, eschewing other unnecessary details, in order to avoid burdening this judgment with the facts which may not be relevant.
(2.) The petitioner is the respondent's wife. It is unfortunate that after their marriage on April 20, 2007 in Delhi, they stayed together hardly for four months. Thus, for almost ten years they have parted company and are living separately. It is not necessary to go into the reasons which led to the matrimonial discord as in the present petition this Court is concerned only with the dispute regarding the rate of maintenance.
(3.) The petitioner had filed an application sometime in June 2009 claiming maintenance under the provisions of Section 12 of the Protection of Women from Domestic Violence Act, 2005 (hereinafter referred to as the 'DV Act'). In that application, apart from other reliefs, she has claimed maintenance as well. Order dated July 05, 2012 was passed by the learned Metropolitan Magistrate granting interim maintenance @ Rs. 2,50,000/- per month with effect from the date of filing of the complaint as well as compensation of Rs. 1,00,000/-. Since the respondent did not honour the said order, the petitioner filed the execution petition for recovery of the arrears of maintenance. In the meantime, the respondent challenged the order of the Metropolitan Magistrate granting maintenance, by filing appeal under Section 29 of the DV Act, in the Court of Additional Sessions Judge, Delhi (for short, the 'ASJ'). In the said appeal, the learned ASJ issued interim directions dated January 10, 2013 for depositing of the entire arrears of maintenance within two months. As this order was not complied with, the appeal filed by the respondent was dismissed on May 07, 2013. This order of dismissal was challenged by the respondent before the High Court. In those proceedings, order dated July 23, 2013 was passed allowing the appellant herein to file the reply, etc. As no stay was granted, order dated July 23, 2013 was challenged by the respondent in this Court by filing a special leave petition. This Court, however, did not entertain the same. At the same time, while disposing of the special leave petition, observations were made to the effect that if the parties apply for mediation, the matter shall be referred to the Delhi High Court Mediation and Conciliation Centre at the earliest. Keeping in view these observations, the High Court referred the dispute to the Mediation Centre at the Delhi High Court and also stayed the execution proceedings in the meantime. Mediation proceedings failed. As a result, the High Court took up the matter on merits and passed orders dated September 10, 2013 directing the respondent to pay Rs. 5,00,000/- on or before September 30, 2013 and another sum of Rs. 5,00,000/- on or before October 31, 2013. The petitioner filed an application seeking modification of these orders and prayed for the directions to the respondent to pay entire arrears of maintenance as per the order of the Family Court in domestic violence proceedings. In the said application only notice was issued and since interim stay on the execution proceedings continued, the petitioner filed special leave petition in this Court for vacation of the interim order passed by the High Court in the execution proceedings. This special leave petition was converted into appeal on grant of leave, in which judgment was delivered on September 18, 2014 allowing the said appeal. Operative portion of the said judgment reads as under:
"31. The issue before the High Court in Crl.MC. No. 1975 of 2013 is limited i.e. whether the sessions court could have dismissed the respondent's appeal only on the ground that respondent did not discharge the obligation arising out of the conditional interim order passed by the sessions court. Necessarily the High Court will have to go into the question whether the sessions court has the power to grant interim stay of the execution of the order under appeal before it.
32. In a matter arising under a legislation meant for protecting the rights of the women, the High Court should have been slow in granting interim orders, interfering with the orders by which maintenance is granted to the appellant. No doubt, such interim orders are now vacated. In the process the appellant is still awaiting the fruits of maintenance order even after 2 years of the order.
33. We find it difficult to accept that in a highly contested matter like this the appellant would have instructed her counsel not to press her claim for maintenance. In our view, the High Court ought not to have accepted the statement of the counsel without verification. The impugned order is set aside.
34. We are of the opinion that the conduct of the respondent is a gross abuse of the judicial process. We do not see any reason why the respondent's petition Crl.MC No. 1975 of 2013 should be kept pending. Whatever be the decision of the High Court, one of the parties will (we are sure) approach this Court again thereby delaying the conclusion of the litigation. The interests of justice would be better served if the respondent's appeal before the Sessions Court is heard and disposed of on merits instead of going into the residuary questions of the authority of the appellate Court to grant interim orders or the legality of the decision of the Sessions Court to dismiss the appeal only on the ground of the non-compliance by the respondent with the conditions of the interim order. The Criminal Appeal No. 23/2012 stands restored to the file of the Sessions Court.
35. We also direct that the maintenance order passed by the magistrate be executed forthwith in accordance with law. The executing court should complete the process within 8 weeks and report compliance in the High Court. We make it clear that such hearing of the Sessions Court should only be after the execution of the order of maintenance passed by the Magistrate.
36. In the event of the respondent's success in the appeal, either in full or part, the Sessions Court can make appropriate orders regarding the payments due to be made by the respondent in the execution proceedings." ;