JUDGEMENT
-
(1.) Leave granted.
(2.) The appellant herein is a Co-operative Society registered
under the provisions of the Karnataka Co-operative Societies Act,
1959. It has established a sugar factory at Hunji, Balki Taluk,
Bidar District, Karnataka with a capacity of 2500 TCD per day
with a provision to expand the same upto 4000 TCD per day. The
appellant had undertaken expansion of its sugar factory from
2500 TCD to 4000 TCD crushing capacity per day and accordingly
invited tenders. The offer of the first respondent which is also a
Co-operative Society registered under the Multi-State Co-
operative Societies Act which is involved in supply, erection and
commissioning of Sugar Plants was accepted in the meeting of
the State Level Advisory Committee held on 10th August, 2000.
The first respondent undertook to design, procure manufacture,
supply transport and deliver at the site and to do the supervision
of erection and commissioning of the Sugar Plant and Machinery
in conformity with the agreed specifications vide agreement dated
1st November, 2000. The clauses of the agreement dated 1st
November, 2000 which are relevant to be noticed are reproduced
as under :
"Clause 5 : Supply, Delivery and
Supervision of Erection and
Commissioning.
Clause 5.1 : The Seller agrees
to supply plant and machinery so
that the supply and erection of the plant
and machinery is completed in all
respects and to the satisfaction of the
Purchaser and the Sugar Plant and
Machinery is Commissioned and made
ready for commercial production and
use by 11th December, 2001.
8.0 TRIALS AND TAKE OVER :
8.1 As soon as the Plant is ready for
commissioning after completion of the
supply of plant and machinery and
erection of the same to the satisfaction
of the purchasers, the sellers on getting
information from the erection contractor
shall notify in writing to the purchasers
specifying the date and time, at least 30
days before the sellers intend to carry
out steam and water trials to enable the
purchasers to arrange for boiler feed
water, fuel, operational staff and
workmen and other facilities. Unless
otherwise agreed by the purchasers and
the sellers, the sellers shall begin the
said trial on the date and time so
notified.
Provided that the water, steam and
vacuum trials shall be conducted by the
sellers for a period of one month before
the commissioning of the plant and
machinery after complete delivery and
erection to the entire satisfaction of the
purchasers.
8.2 After the said steam, water and
vacuum trials have been completed to
the entire satisfaction of the purchasers
and on their furnishing a certificate to
the effect that all the plant and
machinery mentioned in Annexure I to
III have been inspected and approved
by the Inspection Agency, delivered as
per detailed parts list of materials
referred to above, erected and
commissioned under the supervision of
the sellers according to the terms and
conditions of this agreement, the sellers
guarantees given in pursuance of clause
17.2 shall be deemed to have been
fulfilled."
(3.) Bank guarantees were required to be furnished by the
respondent in terms of the agreement. The case of the appellant
is that the first respondent failed to commission the plant in
terms of the agreement. The appellant sent a notice dated 26th
April, 2003 duly putting the respondent on notice of its failure to
commission the plant by the scheduled date i.e. 11th February,
2001 and other revised dates, i.e., 26th January, 2002, 25th
November, 2002, 28th February, 2003 and 25th April, 2003.
Thereafter, a meeting was held between the parties at the
intervention of the Government of Karnataka on 1st July, 2003
where both the parties had agreed as hereunder:
i) 1st respondent shall furnish bank
guarantee for Rs.92.40 lakhs towards
delivery and commissioning of the plant
valid upto 28.02.2004.(Clause 1).
ii) Simultaneously, with the receipt of
the aforesaid bank guarantee, the
petitioner shall release Rs.140.41 lakhs
to the 1st respondent (Clause 4)
iii) 1st respondent will start trial run to
crush 500-1000 tonnes of sugarcane
within 20 days from the date of receipt
of Rs.140.41 lakhs as aforesaid (Clause
6).
iv) The plant will be fully
commissioned by November/December
2003 (Clause 7).;
Click here to view full judgement.
Copyright © Regent Computronics Pvt.Ltd.