MAHARASHTRA ELECTRICITY REGULATORY COMMISSION Vs. RELIANCE ENERGY LTD
LAWS(SC)-2007-8-12
SUPREME COURT OF INDIA
Decided on August 14,2007

MAHARASHTRA ELECTRICITY REGULATORY COMMISSION Appellant
VERSUS
RELIANCE ENERGY LTD Respondents

JUDGEMENT

- (1.) This appeal under Section 125 of the Electricity Act, 2003 (hereinafter for short "the Act") is directed against the judgment and order dated 29th March, 2006 passed by the Appellate Tribunal for Electricity whereby the Appellate Tribunal has allowed the appeals filed by the distribution companies and set aside the orders passed by the Maharashtra Electricity Regulatory Commission (hereinafter for short "The Commission") dated 23.2.2005. The Commission on 3.8.2004 addressed a notice to all its licensees/distribution companies in Maharashtra and made an inquiry from them with regard to raising of the bills by the said licensees/distribution companies on the basis other than the actual meter reading for the relevant period, when large variations in consumption were noticed, or for other reasons. The notice dated 3.8.2004 sent by the Commission to all its licensees/distribution companies reads as under :- "Several instances have come to the Commission's notice of so- called "amendment", "supplementary" or other such bills being raised by some licensees to consumers, often several years later, on a basis other than the actual meter reading for the relevant period, when large variations in consumption are noticed, or for other reasons. Computerised systems have sometimes been put in place which generate such bills automatically. Wide variations observed in recorded consumption and other such apparent anomalies may be useful for monitoring, checking/testing of meters and for taking corrective action. However, billing on a basis other than recorded consumption, and raising amended bills accordingly (often after several years later, and without giving reasons), is not mandated by law. The electricity statutes (in the past, and at present) provide inter alia that, in case of metered consumers, energy consumption charges have to be billed on the basis of meter readings. Moreover, the licensee, and not the consumer, is responsible for maintaining, rectifying, or having such meters replaced where necessary. Thus, no "amendment" bills of the kind referred to above can be raised, and any additional billing has to follow due process and the provision of law. In the context of such "amendment" bills, I am directed to ask that the billing practices followed be immediately reviewed and brought into conformity with the statutory provisions. An affidavit stating the corrective action taken (including withdrawal of all such pending bills, and refund, though adjustment in energy bills or otherwise, of amounts received from consumers on or after 10.6.2003) may be furnished by 3rd September, 2004."
(2.) In response to the said notice all the licensees/distribution companies in Maharashtra made their respective submissions before the Commission explaining under what circumstances the supplementary/amended bills were sent to the consumers. They tried to justify raising of such bills and stated that the these bills were rightly sent as they found that some time the meters were not registering proper consumption and on that basis they tried to justify their action.
(3.) The Commission examined the matter in detail and vide its order dated 23.2.2005 in para 46 directed as under:- "46. After considering all these factors and the submissions made, the Commission directs that the supplementary/amendment bills issued in the circumstances set out at para 42 and 43 above from 10th June, 2003 (the date of coming into force of EA, 2003) and upto notification of the Supply Code. a. should be withdrawn, if due meter testing has not been done with the results intimated to the consumer. b. any amounts collected should be refunded to the concerned consumers (without interest considering the earlier lack of clarity on this meter on the part of the licensees); c. where meters have been found to be defective upon subsequent due testing (and the results intimated to the consumer), the bills may be adjusted for upto 3 months prior to the date of testing or meter replacement, whichever is earlier, and any amounts recovered in excess refunded without interest (in the case of 'stopped' meters, the analogy of the Supply Code provisions should be applied for assessment); d. the above action should be completed by 30th May, 2005, so as to give the licensees more than 3 months' time in view of the work likely to be involved; e. compliance should be submitted on affidavit by 15th June, 2005, with a list of consumers involved, and certifying that no further action remains to be done in terms of this Order." By another order dated 23.8.2005 in the case of M/s. Prayas (Energy Group) Pune, the Commission in para 45 directed as under :- "45. Considering the foregoing, the Commission disposes of Prayas' petition with the following directions, which would apply for the period from 1st June, 2004 (i.e. around 3 months after the detailed Tariff Order dated 10th March, 2004, uptil 19th January, 2005 (following which the Supply code Regulations were notified): (a) no billing using past consumption or some related 'average' basis should be resorted to for more than a period of 3 months. (where average billing has been continuing for more than that period just prior to 1st June, 2004, then it cannot be continued from that date. In case average billing has been resorted to for, say, 2 months prior to that, it can be continued only for upto one month more). During that period 3 months, the meter should have been tested/replaced, with the results intimated to the consumer, and appropriate bill adjustments carried out thereafter (where such average billing is being done on the basis of presumed faulty meter, and where defectiveness of the meter has accordingly been established). If due and timely diligence has not been exercised by the licensee, he cannot claim the right to continue billing on a presumptive, average basis. The same principle will apply to all other situations in which such 'average' billing has been resorted to, except in cases where the meter is not accessible. (However, the Commission notes that, in the case of locked/inaccesible meters, the licensees have recourse to the remedies provided under Section 163 of EA, 2003, and it would be expected that MSEB would exercise it sooner rather than later). (b) In all cases where bills have been raised and/or recoveries made which are not in accordance with (a) above, the bills should be withdrawn and/or amounts refunded to the consumers, through energy bills or other means, as may be relevant, by 30th November, 2005, with interest at the same rate as payable by consumers to MSEB for delayed payments.";


Click here to view full judgement.
Copyright © Regent Computronics Pvt.Ltd.