JUDGEMENT
-
(1.) This appeal under Section 125 of the Electricity Act, 2003 (hereinafter
for short "the Act") is directed against the judgment and order dated 29th March,
2006 passed by the Appellate Tribunal for Electricity whereby the Appellate Tribunal
has allowed the appeals filed by the distribution companies and set aside the orders
passed by the Maharashtra Electricity Regulatory Commission (hereinafter for short
"The Commission") dated 23.2.2005. The Commission on 3.8.2004 addressed a notice
to all its licensees/distribution companies in Maharashtra and made an inquiry from
them with regard to raising of the bills by the said licensees/distribution companies on
the basis other than the actual meter reading for the relevant period, when large
variations in consumption were noticed, or for other reasons. The notice dated
3.8.2004 sent by the Commission to all its licensees/distribution companies reads as
under :-
"Several instances have come to the Commission's notice of so-
called "amendment", "supplementary" or other such bills being
raised by some licensees to consumers, often several years later,
on a basis other than the actual meter reading for the relevant
period, when large variations in consumption are noticed, or for
other reasons. Computerised systems have sometimes been put
in place which generate such bills automatically.
Wide variations observed in recorded consumption
and other such apparent anomalies may be useful for
monitoring, checking/testing of meters and for taking corrective
action. However, billing on a basis other than recorded
consumption, and raising amended bills accordingly (often after
several years later, and without giving reasons), is not mandated
by law.
The electricity statutes (in the past, and at present)
provide inter alia that, in case of metered consumers, energy
consumption charges have to be billed on the basis of meter
readings. Moreover, the licensee, and not the consumer, is
responsible for maintaining, rectifying, or having such meters
replaced where necessary. Thus, no "amendment" bills of the
kind referred to above can be raised, and any additional billing
has to follow due process and the provision of law.
In the context of such "amendment" bills, I am
directed to ask that the billing practices followed be immediately
reviewed and brought into conformity with the statutory
provisions. An affidavit stating the corrective action taken
(including withdrawal of all such pending bills, and refund,
though adjustment in energy bills or otherwise, of amounts
received from consumers on or after 10.6.2003) may be
furnished by 3rd September, 2004."
(2.) In response to the said notice all the licensees/distribution companies in
Maharashtra made their respective submissions before the Commission explaining
under what circumstances the supplementary/amended bills were sent to the
consumers. They tried to justify raising of such bills and stated that the these bills
were rightly sent as they found that some time the meters were not registering proper
consumption and on that basis they tried to justify their action.
(3.) The Commission examined the matter in detail and vide its order dated
23.2.2005 in para 46 directed as under:-
"46. After considering all these factors and the
submissions made, the Commission directs that the
supplementary/amendment bills issued in the circumstances set
out at para 42 and 43 above from 10th June, 2003 (the date of
coming into force of EA, 2003) and upto notification of the
Supply Code.
a. should be withdrawn, if due meter testing has not been
done with the results intimated to the consumer.
b. any amounts collected should be refunded to the
concerned consumers (without interest considering the
earlier lack of clarity on this meter on the part of the
licensees);
c. where meters have been found to be defective upon
subsequent due testing (and the results intimated to the
consumer), the bills may be adjusted for upto 3 months
prior to the date of testing or meter replacement,
whichever is earlier, and any amounts recovered in
excess refunded without interest (in the case of 'stopped'
meters, the analogy of the Supply Code provisions should
be applied for assessment);
d. the above action should be completed by 30th May, 2005,
so as to give the licensees more than 3 months' time in
view of the work likely to be involved;
e. compliance should be submitted on affidavit by 15th
June, 2005, with a list of consumers involved, and
certifying that no further action remains to be done in
terms of this Order."
By another order dated 23.8.2005 in the case of M/s. Prayas (Energy Group) Pune, the
Commission in para 45 directed as under :-
"45. Considering the foregoing, the Commission disposes
of Prayas' petition with the following directions, which would
apply for the period from 1st June, 2004 (i.e. around 3 months
after the detailed Tariff Order dated 10th March, 2004, uptil
19th January, 2005 (following which the Supply code
Regulations were notified):
(a) no billing using past consumption or some related
'average' basis should be resorted to for more than a
period of 3 months. (where average billing has been
continuing for more than that period just prior to 1st
June, 2004, then it cannot be continued from that date.
In case average billing has been resorted to for, say, 2
months prior to that, it can be continued only for upto
one month more). During that period 3 months, the
meter should have been tested/replaced, with the results
intimated to the consumer, and appropriate bill
adjustments carried out thereafter (where such average
billing is being done on the basis of presumed faulty
meter, and where defectiveness of the meter has
accordingly been established). If due and timely
diligence has not been exercised by the licensee, he
cannot claim the right to continue billing on a
presumptive, average basis. The same principle will
apply to all other situations in which such 'average'
billing has been resorted to, except in cases where the
meter is not accessible. (However, the Commission notes
that, in the case of locked/inaccesible meters, the
licensees have recourse to the remedies provided under
Section 163 of EA, 2003, and it would be expected that
MSEB would exercise it sooner rather than later).
(b) In all cases where bills have been raised and/or
recoveries made which are not in accordance with (a)
above, the bills should be withdrawn and/or amounts
refunded to the consumers, through energy bills or other
means, as may be relevant, by 30th November, 2005,
with interest at the same rate as payable by consumers to
MSEB for delayed payments.";