JUDGEMENT
-
(1.) This appeal under Section 125 of the Electricity Act, 2003 (hereinafter for
short "the Act") is directed against the judgment passed by the Appellate Tribunal for
Electricity (hereinafter for short "the Appellate Tribunal") dated 5th April, 2006 in
Appellant's appeal No. 191/2005 and the order dated 2nd June, 2006 passed by the
Appellate Tribunal in Review Petition No. 3/2006 and I.A. No. 60/2006.
(2.) It is not necessary for us to go into the detailed facts. Suffice it to say that the
respondent company approached the Maharashtra Electricity Regulatory Commission
(hereinafter for short referred to as "the Commission") with the grievance that a
demand notice dated 26.8.2002 issued by the Appellant's Wardha office be declared as
illegal and may be set aside and quashed and the respondent company be permitted to
avail power supply to the limit of 90 MVA without recovery of any additional charge
either on account of service connection charges or the service line charges and to
further direct the appellant herein to refund the amount of Rs. 227.9 lakhs so collected
for re-instatement of the contract demand to the original level of 90 MVA along with
interest @ 12% from the date of payment till the date of refund. The respondent
company was a consumer of the Maharashtra State Electricity Board and originally
they had a connection of 90 MVA which was subsequently reduced to 80 MVA and
finally to 56 MVA on a request made by the company. Thereafter again they applied in
June, 2002 for enhancement of their contract demand upto 90 MVA. Their request
for enhancement of contract demand upto 90 MVA was granted though it was clearly
mentioned in the order dated 12.8.2001 while reducing the contract demand to 56
MVA that in case enhancement of contract demand was subsequently required by the
respondent company, it would attract payment of service line and other charges as per
then prevailing conditions of supply. However, the regular supply of 90 MVA was
restored on the request of the respondent company. The supply of 90 MVA was
restored in June, 2002 and thereafter a demand was raised in terms of letter dated
02.08.2001 for service line charges, which was agreed to be paid by the respondent
company, but in installments. Aggrieved against the said order the respondent-
company filed a petition before the Commission on the ground that the demand of
Rs.227.9 lakhs so raised for reinstatement of contract demand of 90 MVA is not
proper. An objection was raised before the Commission that the Commission has no
jurisdiction in the matter in view of Section 42 of the Act and that the consumer should
approach the Consumer Grievance Redressal Forum and thereafter, if still aggrieved,
the Ombudsman created under the Act for redressal of their grievances. The
Commission over-ruled this objection by making a reference to some decision of the
Bombay High Court and proceeded to assume jurisdiction and directed the refund of
the aforesaid amount to the respondent company.
(3.) Aggrieved against the said order dated 18th October, 2005, the Maharashtra
State Electricity Distribution Company Ltd. (hereinafter for short "MSEDCL")
approached the Appellate Tribunal for Electricity created under the Act. The
Appellate Tribunal vide its order dated 5th April, 2006 affirmed the order passed by
the Commission. Thereafter a review petition was filed by the MSEDCL before the
Appellate Tribunal, which was also rejected vide order dated 2nd June, 2006.
Aggrieved against both these orders, the MSEDCL has approached this
Court by the present appeal under Section 125 of the Act.;
Click here to view full judgement.
Copyright © Regent Computronics Pvt.Ltd.