JUDGEMENT
-
(1.) Leave granted.
(2.) Challenge in this appeal is to the order passed by a
Division Bench of the Allahabad High Court holding that the
demand raised by the appellant-Corporation through various
bills purporting to realize penalty for violation of peak hour
restrictions cannot be maintained. The question was whether
one Meter Reading Inspection Report (in short 'MRI') should be
construed as single violation of the commercial restrictions
irrespective of the fact that a number of contraventions might
have been made by consumers during the period covered by
the said report.
(3.) The State Government of Uttar Pradesh issued a
notification under Section 22-B of the Electricity Act, 1910
(hereinafter to be referred to as "the Act of 1910") known as
the U.P. Electricity (Regulation of Supply, Distribution,
Consumption and Use) Order, 1977 which was published in
the Official Gazette. This order was amended on 30-4-1984,
known as the U.P. Electricity (Regulation of Supply,
Distribution, Consumption and Use) (1st Amendment) Order,
1984 by which clause 9 of the 1977 Order was amended and it
was substituted by the following:
"9. (1) Without prejudice to the provisions
contained in Section 42 of the Indian
Electricity Act, 1910, all Chief Zonal
Engineers, Superintending Engineers,
Executive Engineers, Assistant Executive
Engineers and Assistant Engineers of the
Uttar Pradesh State Electricity Board, the
Chief Electrical Inspector, all Deputy
Electrical Inspectors and all Assistant
Electrical Inspectors to the State
Government are authorised to disconnect
the supply summarily without notice in
relation to such installation as are found
upon inspection made by them to have
contravened the provisions of this Order.
The supply shall remain disconnected for
the period specified below
(a) Contravention first in point of time
5 days
(b) Contravention second in point of time
10 days
(c) Contravention third in point of time
20 days
(d) Contravention beyond third point of
time Permanently:
Provided that for the purposes of this
clause any contravention prior to 1-5-
1984 shall not be taken into account.
(2) In addition to above, such consumers
shall be liable to pay the penalty for each
contravention as follows:
(a) Consumers having contracted load up
to 100 kVA, at Rs 50 per kVA on their
contracted load.
(b) Consumers having contracted load
above 100 kVA and up to 500 kVA at
Rs.30 per kVA on their contracted load
subject to minimum of Rs 5000.
(c) Consumers having contracted load
above 500 kVA at the rate of Rs 20 per
kVA on their contracted load subject to
minimum of Rs 15,000.
The reconnection shall only be done after
payment of penalty and expiry of the
above specified disconnection period
whichever is later.";
Click here to view full judgement.
Copyright © Regent Computronics Pvt.Ltd.