JUDGEMENT
-
(1.) This appeal is directed against the judgment of the division bench of the Patna High court dated 7/9/1979 in Civil Writ Jurisdiction Case No. 1710 of 1978.
(2.) The respondent filed the writ petition challenging the legality of the notice served by the appellant issued in exercise of power under Section 24 (1 of the Indian Electricity Act, 1910 (hereinafter referred to as 'the Act') inter alia on the ground that a bona fide dispute exists between the licensee and the consumer of electric energy and as such the provisions of Section 24 (1 of the Act will not apply. The case of the respondent-consumer is that the appellant has been supplying energy to the respondent-hotel but the said respondent has not entered into any agreement and therefore the appellant is entitled to charge on the basis of the actual consumption and not on the basis of any contract demand. The appellant, however, submitted bills in respect of the energy consumed on the basis of the contract demand which the respondent did not pay and for such default in payment of the amount charged under the bills the appellant issued notice of discontinuance under Section 24 of the Act. According to the respondent's case the bills submitted by the appellant being disputed, no notice could have been issued by the appellant under Ss. (1 of Section 24 and the matter can only be referred to the Electrical Inspector for a decision as provided under Ss. (2 of Section 24. The appellant disputed the aforesaid stand of the respondent and submitted that the respondent having failed to pay the bills raised by the appellant in respect of the energy consumed, the appellant was fully justified in issuing notice under Section 24 (1 of the Act and there is no illegality in the same. The High court by the impugned judgment came to the conclusion that no agreement had been entered into between the licensee, namely, the Bihar State Electricity Board and the consumer, the respondent. It further came to the conclusion that in the absence of any agreement between the parties the Board was not entitled to raise the bills on the basis of the contract demand and can only charge on the basis of the actual consumption of energy. Finally, the High court came to the conclusion that there existed a bona fide dispute between the licensee and the consumer, and therefore, until that dispute is resolved by a determination made by the Electrical Inspector under Ss. (2 of Section 24, the licensee was not entitled toissue notice of disconnection in exercise of power under Ss. (1 of Section 24 of the Act. The High court, therefore, quashed the notice of demand and the threat of disconnection and issued a mandamus to the licensee not to disconnect the supply line so long as the dispute is not resolved in accordance with law. The High court also further held that until the dispute is finally resolved, the consumer would be liable to be charged on the basis of actual consumption of energy. The amount of accumulated arrears which was indicated in the notice of disconnection to the licensee was Rs. 3,01,449.30 up to March 1979 which demand was quashed by the High court by the impugned judgment. This court on 1/5/1981 directed that the respondents shall pay the amount due on the bills submitted to them by the appellant for the actual consumption and future bills will be paid by the respondents from time to time on the basis of actuals and such submission of bills and payments will be without prejudice to the rights and contentions of the parties. By another order dated 5/5/1982 this court further indicated that for the time being the Board will not collect any energy charges by the application of the multiplier of the two. Thereafter, as the respondent failed to pay the bills issued by the Board, the supply of electricity to the respondent was disconnected on 9/5/1984. The respondent, therefore, approached this court by filing an application for necessary direction to the Board to restore the connection of electricity supply and to injunct the Board from disconnecting the supply without permission of this court during the pendency of the appeal, which was registered as CMP No. 23405 of 1984. In the said application it was alleged that the appellant-Board went on giving inflated bills based on erroneous conclusion on the basis of 315 KVA of maximum contract demand which has already been quashed by the Patna High court and which is contrary to the interim orders issued by this court as stated earlier. This application was disposed of by this court with the following direction:
"The counsel for both the parties have jointly submitted before me that the parties are agreeable that the correct amount payable by the respondent in the appeal by way of charges for actual consumption of electrical energy as per tariff rates applicable may be determined by any officer not below the rank of Chief Engineer nominated by the secretary, Department of Energy, Govt. of India. This suggestion appears to me just and fair which is accordingly accepted and the secretary, Department of Energy will forthwith nominate any one officer under him of the rank indicated above to go into the question as to what amount, if any, remains payable up to date by the Hotel Satkar (P) Ltd. to the Bihar State Electricity Board, Patna by way of consumption charges taking into account actual consumption. Such determination will be made after hearing both the parties of their representatives at Delhi or at Patna as will be convenient to the officer nominated by the secretary, Department of Energy. The entire process of determination of the amount should be completed within four weeks from today. The respondent shall file an undertaking during the course of the day today to pay to the Bihar Electricity Board within one week from the date of such determination of the exact amount by the officer nominated by the secretary, Department of Energy. Subject to the fulfilment of this condition the Bihar State Electricity Board is hereby directed to restore forthwith the electric connection to the respondent-Hotel Satkar (P) Ltd. If the respondent- Hotel Satkar fails or defaults in the payment within one week of 640 determination of the amount due, it will be open to the Bihar State Electricity Board to disconnect electric connection. The payment to be made by the respondent in pursuance of this order will be without prejudice to the rights and contentions raised in the appeal pending before this court. "
(3.) Pursuant to the aforesaid order of this court the Chief Engineer, central Electricity Authority was nominated by the secretary, Department of Power, Ministry of Energy to go into the question as to what amount, if any, remains payable up to date by the respondent. The said Chief Engineer heard the parties and gave opportunity to present their respective case and after analysing all the relevant papers and documents produced before him, came to the conclusion that for the period from April 197 7/02/1984 the respondent is liable to pay the appellant a sum of Rs. 9,68,335.67 for the energy consumed on the basis of actual consumption and out of the said amount the consumer has paid a total of Rs. 5,83,776.34 and, therefore, the outstanding dues till February 1984 work out to Rs. 3,84,559.33. On behalf of the respondent an objection to the aforesaid report of the Chief Engineer has also been filed in this court.;
Click here to view full judgement.
Copyright © Regent Computronics Pvt.Ltd.