JUDGEMENT
-
(1.) The assail in the present appeal, by special leave, is to the judgement and order passed by the National Consumer Disputes Redressal Commission, New Delhi (for short "the National Commission") in Revision Petition No. 258 of 2013 whereby the said Commission has approved the decision of the State Consumer Disputes Redressal Commission, Hyderabad which had reversed the view of the District Consumer Forum that the complainant is a "consumer" within the definition under Section 2(1)(d) of the Consumer Protection Act, 1986 (for brevity, "the Act") as the agreement of the appellant with the respondents was not a joint venture. The District Forum had arrived at the said decision on the basis of legal principles stated in Faqir Chand Gulati v. Uppal Agencies Pvt. Ltd. and anr., 2008 10 SCC 345. The State Commission had opined that the claim of the appellant was not adjudicable as the complaint could not be entertained under the Act inasmuch as the parties had entered into an agreement for construction and sharing flats which had the colour of commercial purpose. Thus, the eventual conclusion that the State Commission reached was that the complainant was not a consumer under the Act. The said conclusion has been given the stamp of affirmance by the National Commission.
(2.) The factual score that is essential to be depicted is that the appellant is the owner of the plot nos. 102, 103 and 104 in survey no. 13/1A2, Patta no. 48 admeasuring 1347 sq. yards situate at Butchirajupalem within the limits of Visakhapatnam Municipal Corporation. Being desirous of developing the site, the land owner entered into a Memorandum of Understanding (for short "the MOU") with the respondents on 18.07.2004 for development of his land by construction of a multi-storied building comprising of five floors, with elevator facility and parking space. Under the MOU, the apartments constructed were to be shared in the proportion of 40% and 60% between the appellant and the respondent No. 1. Additionally, it was stipulated that the construction was to be completed within 19 months from the date of approval of the plans by the Municipal Corporation and in case of non-completion within the said time, a rent of Rs. 2000/- per month for each flat was to be paid to the appellant. An addendum to the MOU dated 18.07.2004 was signed on 29.04.2005 which, inter alia, required the respondents to provide a separate stair case to the ground floor. It also required the respondents to intimate the progress of the construction to the appellant and further required the appellant to register 14 out of the 18 flats before the completion of the construction of the building in favour of purchasers of the respondents.
(3.) As the factual matrix would further unfurl, the plans were approved on 18.05.2004 and regard being had to schedule, it should have been completed by 18.12.2005. However, the occupancy certificates for the 12 flats were handed over to the occupants only on 30.03.2009, resulting in delay of about three years and three months. In addition, the appellant had certain other grievances pertaining to deviations from sanction plans and non-completion of various other works and other omissions for which he claimed a sum of Rs.19,33,193/- through notices dated 6.6.2009 and 27.6.2009. These claims were repudiated by the respondents vide communications dated 17.07.2009 and 16.08.2009.;
Click here to view full judgement.
Copyright © Regent Computronics Pvt.Ltd.