RASHTRIYA ISPAT NIGAM LTD. Vs. M/S. PRATHYUSHA RESOURCES & INFRA PRIVATE LIMITED AND ANR.
LAWS(SC)-2016-2-35
SUPREME COURT OF INDIA (FROM: ANDHRA PRADESH)
Decided on February 12,2016

RASHTRIYA ISPAT NIGAM LTD. Appellant
VERSUS
M/S. Prathyusha Resources And Infra Private Limited And Anr. Respondents

JUDGEMENT

- (1.) The present appeal is filed by the appellant challenging the judgment and order dated 16.12.2005 passed by the Division Bench of the High Court of Judicature for Andhra Pradesh at Hyderabad, whereby the order dated 6.7.2004, passed by the learned District Judge, Vishakhapatnam, was set aside and the arbitration award was confirmed.
(2.) The appellant - Rashtriya Ispat Nigam Ltd., which is popularly known as Visakhapatnam Steel Plant, is a Government of India Undertaking, inter alia, engaged in manufacture and sale of steel products and pig iron in the domestic and export markets. Respondent No.1 is a transporter, stevedoring, clearing & forwarding agent at Visakhapatnam. The appellant floated a tender vide Notification dated 31.03.1992 for transportation of pig iron etc. from its Visakhapatnam Steel Plant to the Visakhapatnam Port area. Respondent No.1 being the successful bidder, was awarded the work order on 28.07.1992. An Agreement was entered into between the appellant and respondent No.1 on 24.02.1993 which was to expire on 31.03.1993. But owing to circumstances, the work was extended several times and the contract was finally completed on 23.10.1997. Issues arose as to the rate of escalation based on the base year 1992 or 1994. Respondent No.1 submitted final bill having three annexures out of which first two were admitted, however, the appellant rejected the third one which was as to deciding the base year for calculating escalation.
(3.) The Arbitration Tribunal (consisting of a retired Judge of the High Court) decided the five issues framed in favour of the respondent/claimant whereby the base year was adjudged as 1992, the bar of limitation was negated and the calculations made by the Claimant were upheld. The appellant challenged the said award under Section 34 of the Arbitration Act, 1996 before the Ld. District Court which set aside the award as the relief was barred by limitation. Upon appeal under Section 37 of the Act by the respondent/claimant, the High Court set aside the order of the District Judge and upheld the award of the Arbitrator.;


Click here to view full judgement.
Copyright © Regent Computronics Pvt.Ltd.