JUDGEMENT
D.Y.CHANDRACHUD,J. -
(1.) The Petitioner is a company incorporated in the US. The Respondent is incorporated in Turkey. The Respondent was awarded a contract for the
construction of a pipeline by the Gas Transmission Company Ltd., Bangladesh.
A Letter of Intent was issued by the Respondent to the Petitioner on 16
April 2012 for performing Horizontal Directional Drilling works for six river crossings
under the above-mentioned project in Bangladesh. A detailed work order was
issued on 12 June 2012 to the Petitioner for a total contract price of USD
7,225,000/-. The work to be executed by the Petitioner involved the installation of thirty inch diameter and six inch diameter gas pipelines under six rivers in
Bangladesh. According to the Petitioner the effective date of the contract was 16
April 2012, while the scheduled date of completion was on 13 March 2013. The
Petitioner is stated to have furnished a performance bank guarantee equivalent
to ten per cent of the contract price. Clause 24 of the work order contained an
Arbitration Agreement in the following terms :-
"24.0 Disputes and Arbitration
24.2 Arbitration : In case the amicable resolution or settlement is not reached between the Parties within a period of 30 days from the day on which the dispute(s) or difference(s) arose, such dispute(s) or difference(s) shall be referred to a sole Arbitrator for settlement by way of arbitration in accordance with the provisions of the Arbitration and Conciliation Act 1996 of Government of India or any applicable law on arbitration that may be in force then, and any amendments made thereto. The sole arbitrator shall be appointed by the mutual consent of both the Parties. The decision of the Arbitrator shall be final and binding on both the Parties. The venue of such arbitration shall be at New Delhi, India. The Language of the arbitration proceeding shall be in English. The existence of any dispute(s) or difference(s) or the initiation or continuance of the arbitration proceedings shall not permit the Parties to postpone or delay the performance by the Parties of their respective obligations under this indenture".
According to the Petitioner, four letters of credit were opened by the
Respondent so as to facilitate the completion of four crossings. The
remaining letter of credits, it is alleged, were not opened. According to the
Petitioner, it successfully completed work under all the six crossings and its
bank guarantee was allowed to lapse.
(2.) Disputes have arisen between the parties, resulting in an exchange of e-mails. The Petitioner has a claim for unpaid dues. The Petitioner
invoked arbitration by an e-mail dated 2 November 2015 addressed by its
advocate to the respondent. The Petitioner claimed an amount of USD
38,13,723.76 together with interest by its e-mail and suggested the names of two former judges of the Delhi High Court. The Petitioner sought the
concurrence of the Respondent to the appointment of one of them as sole
arbitrator, in terms of the arbitration agreement. Finding no response,
these proceedings were instituted under Section 11(5) of the Arbitration and
Conciliation Act, 1996.
(3.) Notice was issued in these proceedings on 8 March 2016. On 7 October 2016 the Respondent informed this Court that it was willing to negotiate an amicable settlement with the Petitioner and would either
finalize a settlement or file its objections to the petition for appointment of
an arbitrator within four weeks. Neither has any settlement been arrived at
between the parties nor has a reply been filed to the Arbitration Petition.;
Click here to view full judgement.
Copyright © Regent Computronics Pvt.Ltd.