JUDGEMENT
R.F.NARIMAN,J. -
(1.) These appeals have been argued over a number of days, but ultimately the points raised in them lie within a narrow compass.
(2.) On 19.1.2005, the Central Government, in exercise of powers under Section 63 of the Electricity Act, 2003 issued guidelines for a
tariff based competitive bid process to be initiated by distribution
licensees /procurers for procurement of power from generating
companies. The electricity to be procured by such procurers is for the
purpose of distribution and retail supply to consumers generally. On
10.2.2006, in pursuance of these guidelines, procurers in different States, namely, appellants 1 to 3 and respondents 5 to 15 (in Civil
Appeal Nos.5239-5240 of 2016) nominated Power Finance
Corporation Limited, a Government of India undertaking as the Nodal
Agency to complete a competitive bid process for development of an
ultra mega power project based on linked coalmines using super
critical technology of units of 660 mega watts (MW) each, plus or
minus 20%, in Sasan District, Singrauli, Madhya Pradesh. On
10.2.2006, Sasan Power Limited was incorporated as a special purpose vehicle by Power Finance Corporation in order to implement
the aforesaid purpose. On 1.8.2007, based on the competitive
bidding process held by Power Finance Corporation, Reliance Power
Limited, having quoted the lowest amount, was selected as the
successful bidder, and a letter of intent was issued to Reliance Power
Ltd. The quoted tariff, year by year, for a period of 25 years, which
was accepted and incorporated as Schedule 11 in the Power
Purchase Agreement dated 7.8.2007 (PPA) had tariffs at an
extremely depressed rate for the first two years, after which the tariffs
were fixed at a significantly higher rate. On the very day that the PPA
was executed between Sasan Power Limited and the procurers for
generation and sale of electricity, 100% share holding of the special
purpose vehicle was acquired by Reliance Power Limited. The PPA
contains detailed clauses with respect to generation of power and the
tariffs payable for the period of 25 years. Apart from other provisions,
we are really concerned with Article 6 read with Schedule 5 which
provides for pre-conditions to be satisfied for declaration of a
generating unit as Commercial Operation Date, "COD", namely
readiness to commence commercial operations. This happens only
when a performance test, by operating the generating unit at 95% of
the contracted capacity as existing on the Effective Date on a
continuous running basis for 72 hours, has been certified by an
independent engineer, by giving a final test certificate to the aforesaid
effect. The PPA also contains various other clauses which will be set
out during the course of this judgment.
(3.) The bone of contention in these matters is whether the COD for Unit No.3, which was the first Unit to be commissioned, had been
achieved on 31.3.2013. If it had, then under Schedule 11 to the
PPA, the entire first year would get exhausted in one day, i.e., 31 st
March being the end of the contract year, for which tariff payable
would be at the rate of 69 paise per unit. If not, then it is only on and
from the commencement of COD that such year would begin, which,
according to the appellants before us, would only begin on 16.8.2013
when a final test certificate in accordance with Article 6 of the PPA
was given by the independent engineer to the effect that 95% of the
contracted capacity had been achieved for a continuous period of 72
hours. We are informed that if the COD is said to be on 31.3.2013,
as has been held by the Appellate Tribunal, the consumers would
have to pay a sum of over 1000 crores, being the differential tariff
that would apply.;
Click here to view full judgement.
Copyright © Regent Computronics Pvt.Ltd.