JUDGEMENT
A.M.KHANWILKAR, J. -
(1.) Application for early hearing is allowed.
(2.) The respondent no.1 had filed a writ petition under Article 226 of the Constitution of India bearing Writ Petition (MD) No.9854 of
2012, which was allowed by the learned Single Judge on the following terms:
"6. In view of the above, this Court is of the view that since the petitioner is not inclined to put up further construction, there is no need for the petitioner to get permission from the Local Planning Authority. Under such circumstances, recording the undertaking given by the petitioner, this Court is inclined to give a direction to the respondents to grant renewal of permission for the construction, so that the petitioner can complete the building work which was already constructed. The affidavit of undertaking given by the petitioner is placed on record. The respondents are directed to grant renewal of permission so that the petitioner can finish the building which was already constructed by her, within a period of two weeks from the date of receipt of a copy of this order.
7. Accordingly, the writ petition is disposed of No costs."
The appellant - Corporation filed a Writ Appeal being Writ
Appeal (MD) No.763 of 2013. That was dismissed by the Division
Bench vide order dated 21.8.2013. These decisions are the subject
matter of the present appeal filed by the Corporation.
(3.) The principal issue considered by the learned Single Judge of the High Court was whether the appellant was the Competent
Authority to grant an extension of time to the respondent no.1 for
completing the construction of the building, which was commenced
on the basis of a sanction given by the Local Planning Authority,
Madurai on 25.04.2009. The sanction given by the said Authority
was attached with a condition that the construction of the proposed
building upto 11 floors, should be completed by the respondent
no.1 within two years therefrom. The respondent no.1 within such
period could construct only upto 6 floors. As the respondent no.1
was unable to comply with the condition of completing the
construction as per the sanctioned plan within two years, he
submitted an application on 11.04.2011 to the appellant -
Corporation for an extension of time. The respondent no.1 was
called upon to submit an application in Form 8, which requirement
was compiled by him. The appellant, however, affixed a notice on
the construction site purported to be under Sections 282, 296(1)
and 296(2) of the Madurai City Municipal Corporation Act, pointing
out that the respondent no.1 had deviated from the original plan in
respect of (a) lift (b) stair case to the building and (c) instead of a
swimming pool open to the sky, a hall was constructed on the first
floor of the building under construction. Based on the said
proceedings, the Corporation rejected the application submitted by
respondent no.1 for extension of time to complete the construction,
vide order dated 21.06.2012. The respondent no.1 challenged that
order by way of writ petition. During pendency of the said writ
petition, the respondent no.1 filed an affidavit cum undertaking
assuring the Authority that he would complete the construction of
the building only up to Ground floor + 6 floors + (1 light roofing
ceiling) and would take corrective steps to remedy the deviations
pointed out in the notice affixed on the construction site. The
appellant, however, contended that it was not the Competent
Authority to grant extension of time as the sanction was originally
granted by the Authority under the Town and Country Planning
Act. This contention did not find favour with the learned Single
Judge. As a result, the learned Single Judge allowed the writ
petition filed by respondent no.1 in terms of order dated
21.08.2013. The operative part of the said order has been reproduced in paragraph 2 above. For the same reason, the Division
Bench of the High Court declined to interfere in the writ appeal filed
by the appellant.;
Click here to view full judgement.
Copyright © Regent Computronics Pvt.Ltd.