NARIMAN,J. -
(1.) We have heard Shri Rakesh Khanna, learned senior counsel
appearing for the appellants for quite some time, and Shri. Gurukrishna
Kumar, learned senior counsel appearing for the respondent in reply.
Though Shri Rakesh Khanna has taken us through the PPA, various
documents, and various orders in great detail, we do not find it
necessary to go into any of these for the reason that we find that the
appellants had set up various expert committees to go into the bone of
contention in this appeal, namely, project cost and completed cost.
(2.) We find that M/s. K.P.C.L (M/s. Karnataka Power Corporation Ltd.) had been appointed by them in order to determine the project cost which was
determined at L 73.40 crores. M/s. Tamil Nadu Electricity Generation and
Distribution Corporation Ltd. (TANGEDCO), another expert, arrived at a
finding of L 82.11 crores, which was reconfirmed by a subsequent report,
and ultimately arrived at a figure of L 79.439 crores with other issues
which were to be decided separately. A joint exercise between the
appellants and respondent, also carried out in April, 2010, where a
figure of L 76.14 crores was arrived at, and the balance of L 8.82 crores
in respect of IDC, that is, interest during construction and preliminary
expenses was left to be examined by the Central Electricity Authority.
The Central Electricity Authority also came out with three separate
reports in which it arrived at certain figures of project cost. Finally,
the administration appointed a five member committee after all these
reports, and in 2013, this five member committee ultimately arrived at L
70.61 crores as the final project cost. This was as follows :
JUDGEMENT_106_LAWS(SC)9_2016.jpg
(3.) Subsequently, it has been stated that the said report of the five member committee has been accepted by the Administration. The Respondent
had prayed that the Hon'ble Commission determine the project cost and
tariff thereon in accordance with the provisions of PPA/Techno Economic
Clearance issued by A&N Administration and the report of the five members
committee constituted by the A & N Administration for the purpose of
determination of the cost of the project as L 70.61 crores.;