UNION OF INDIA Vs. V S ENGINEERING P LTD
LAWS(SC)-2006-11-66
SUPREME COURT OF INDIA (FROM: ANDHRA PRADESH)
Decided on November 16,2006

UNION OF INDIA Appellant
VERSUS
V.S. ENGINEERING (P) LTD. Respondents

JUDGEMENT

A. K. Mathur, J. - (1.) These appeals are directed against the judgment and order passed by the High Court of Andhra Pradesh. By the impugned order dated 27.4.2001 a batch of writ petitions were disposed of including the one before us whereby the High Court appointed arbitrator under Section 11 of the Arbitration and Conciliation Act, 1996 (hereinafter to be referred to as the Act). In the present appeals, we are concerned with Writ Petition No. 2465 of 2001 [Union of India and Anr. v. M/s.V. S. Engineering (P) Ltd. and Anr.]. So far as order dated 27.4.2001 passed by the Division Bench of the High Court is concerned, all the issues raised in that order has already been decided by this Court in the case of SBP and Co. v. Patel Engineering Ltd. and Anr. [(2005) 8 SCC 618] by a seven Judge Bench of this Court. Therefore, no purpose will be served by examining the validity of the order of the Division Bench of the High Court challenged in this present appeal as all issues are covered in the decision of SBP and Co. (supra), therefore this appeal is accordingly disposed of in the light of the aforesaid decision.
(2.) Brief facts giving rise to another appeal are that M/s. V. S. Engineering Private Limited, Hyderabad was awarded the work of supply and stacking of 50mm machine crushed stone ballast at Nallapadu Depot and loading the same into B.T.Wagons by Mechanical/ Manual means for a quantity of 1.8 lakh cum at the value of Rs. 5,02,20,000/ . The agreement No.GM/W/SC/93/2 providing payment of mobilization advance and machinery and plant advance was executed by the contractor on 19.4.1993. The completion period was 39 months as per the acceptance letter dated 27.1.1993. As per the agreement the work was to be commenced from 26.4.1993 and completed by 26.4.1996 supplying the ballast at the rate of 60,000 cum per annum. As the contractor could not commence the work as per the tender conditions and supplied only 88214 cum up to November, 1997 penalty for an amount of Rs.1,01 crore was recovered from the running bills of the contractor. The appellant did not agree to the request of the contractor for waiver of penalty and rescheduling of supply. Therefore, a dispute arose between the parties and the contractor sought appointment of an arbitrator under clause 64 of the General Conditions of Contract. In pursuance of the contractors demand the Arbitral Tribunal was appointed to adjudicate the contractors claim. The Arbitral Tribunal initiated the proceedings and the contractor submitted his claim statement before the Arbitral Tribunal. Subsequently, the contractor filed an Arbitration Application No. 60 of 1998 dated 16.10.1998 before the High Court of Andhra Pradesh at Hyderabad under section 11 of the Act, seeking appointment of an Arbitrator to resolve the dispute emanating from the agreement dated 19.4.1993. The appellant Union of India contested the arbitration application filed by the respondent by filing a counter and denying the allegations. It was pointed out that it was wrong to say that the payment was not done for the work done. It was alleged that the payment was made as per the terms of the contract and there was no delay on the part of the Railway. It was also contended that the request for referring the dispute for arbitration has to be done in accordance with Clauses 63 and 64 of the General Clauses of Contract. As per Clause 63, on receipt of the application the Railway had to notify the decisions on all matters including the matters which came up under the caption excepted matters. The respondent subsequently made a request for referring the matter to Arbitral Tribunal, The General Manager of the Railways as per Clause 64 of the General Conditions of Contract accepted the request of the respondent for referring the dispute to the Arbitral Tribunal and accordingly, a letter was sent on 5.5.1998 furnishing four names of Railways Officers out of which the respondent had to nominate up to two names which was the requirement in accordance with clause 64 (3) (a) (ii) of the General Conditions of Contract. The respondent chose one name i.e. Shri R.N. Raghavan out of the four names given to him and the dispute was referred to the Arbitral Tribunal on 20.8.1998. Thereafter some other Railway Official was appointed. Some claims were not referred to the Arbitral Tribunal. Meanwhile, the contactor filed petition in the High Court. The High Court on 28.11.2000 appointed Mr.Justice Y. V. Narayana as Arbitrator to resolve the disputes and referred all 14 claims and also fixed the fee at Rs. 2 lac. Aggrieved by the order dated 28.11.2000 passed in Civil Miscellaneous Petition No. 60 of 1998, the appellant filed a writ petition before the High Court challenging the order of the learned Single Judge appointing the Arbitrator before the Division Bench. The Division Bench clubbed together large number of matter including various issues pertaining to Arbitration Act, 1996 and decided by its order dated 27.4.2001. This order was also challenged by Union of India by filing the present appeal. The Division Bench of the High Court by this order disposed of Union of Indias appeal pertaining to this subject matter and directed that in view of the peculiar facts of this case that since General Manager of the Railway has already constituted an Arbitral Tribunal, the appellant should approach the learned Single Judge for modification/ recalling the aforesaid order dated 28.11.2000. Pursuant to that the appellant approached the learned Single Judge praying for modification of the order. Learned Single Judge dismissed the aforesaid application by order dated 21.2.2002. While dismissing the application, learned Single Judge observed as follows : " As this court is of the opinion that the Arbitral tribunal constituted by the General Manager is impliedly set aside and the matters referred are already withdrawn by referring the same to the sole Arbitrator appointed by this Court, the question of functioning of the Arbitral Tribunal constituted by the General Manager, Railways, does not arise." Hence, aggrieved against this order the present Special Leave Petition was filed and leave was granted. Hence both the present appeals have come up before us for final disposal.
(3.) Learned Additional Solicitor General appearing for the appellant Union of India has pointed out that as per Clauses 63 and 64 of the General Conditions of Contract, this Court in no uncertain terms has held that the Arbitral Tribunal has to be constituted as per the General Conditions of Contract, the High Court should not interfere under Section 11 of the Act and the High Court should accept the Arbitral Tribunal appointed by the General Manager, Railway. In this connection, learned ASG invited our attention to a decision of this Court directly bearing on the subject in Union of India and Anr. v. M.P.Gupta [(2004) 10 SCC 504] wherein a similar question with regard to appointment of Arbitral Tribunal for the Railways with reference to Clause 64 of the General Conditions of Contract came up before this Court and this Court held that where two gazetted railway officers are appointed as the Arbitral Tribunal, the High Court should not appoint a retired Judge of the High Court as a sole Arbitrator and the appointment of sole arbitrator was set aside. The conditions of Clauses 63 and 64 of the General Conditions of Contract are almost analogous to the one we have in our hand. In that case also relying on Clause 64 of the contract a three Judge Bench presided over by the Chief Justice of India observed as follows : "In view of the express provision contained therein that two gazetted railway officers shall be appointed as arbitrators, Justice P.K.Bahri could not be appointed by the High Court as the sole arbitrator. On this short ground alone, the judgment and order under challenge to the extent it appoints Justice P.K.Bahri as sole arbitrator is set aside. Within 30 days from today, the appellants herein shall appoint two gazetted railway officers as arbitrators. The two newly appointed arbitrators shall enter into reference within a period of another one month and thereafter the arbitrators shall make their award within a period of three months." Earlier also in the case of Datar Switchgears Ltd. v. Tata Finance Ltd. and Anr. [ (2002) 8 SCC 151] their Lordships have observed that the arbitrator should be appointed within thirty days on demand being made by the other party and the appointment could still be made but before the other party moves the Court under Section 11 of the Act. It was observed that once the other party moves the court the right to make the appointment ceases to exist. In the present case as it appears that the General Manager, Railway has already appointed the arbitrator but despite this, learned Single Judge has overruled the objection of the Union of India and appointed learned Judge of the High Court as arbitrator.;


Click here to view full judgement.
Copyright © Regent Computronics Pvt.Ltd.