JUDGEMENT
K.RAMASWAMY,J. -
(1.) Special leave granted.
(2.) The respondent had entered into a contract on 7-1-1983 to construct 13 units of Type-V Quarters at the estimated cost of Rs 27,34,000. He was to
complete the construction and hand over possession on 13-8-1984. Despite
extension of the time on 7 occasions, finally up to 30-6-1988, the
construction was not completed resulting in termination of the contract.
As up to 34th bill the appellant paid to the respondent a sum of Rs
24,34,100.91 ps. towards the executed work. The contractor laid proceedings under Section 20 of the Arbitration Act, 1940 (for short 'the
Act') for reference to arbitrate the disputes. The joint arbitrators
appointed thereon entered upon reference on 10-4-1989 and nominated Mr A.
Biswas, the second respondent as an umpire. Since the joint arbitrators
could not make and publish the award within the time, the umpire was
called upon to enter upon the reference. Accordingly on 25-4-1990 the
umpire had entered upon the reference and made an interim award on
26-7-1990 for a sum of Rs 6,02,000. The contractor laid his claim for a sum of Rs 37,37,885. The appellant laid counter-claim for Rs 9,49,701.50
ps. On 3-9-1990 the appellant requested the umpire to consider the
counter- claim. On 4-9-1990, the umpire refused to consider the
counter-claim on the ground of belated counter-claim. On request the time
to make and publish the award was extended up to 31-1-1991. The umpire
held finally sitting on 19-12- 1990 (it is disputed across the bar by the
contractor) and he made the award on 24-12-1990 for a sum of Rs 24,18,320
in favour of the contractor. The umpire also awarded interest at 18% up
to 10-4-1989 and post-award interest. He did not grant any pendente lite
interest. The appellant challenged the award on diverse grounds under
Sections 30 and 33 of the Act. Ultimately the Division Bench of the
Calcutta High Court in Appeal No. 453 of 1991 dated 16-9-1992 confirmed
the award for a sum of Rs 20,07,320 and awarded pendente lite interest.
On a review, it was held by an order dated 4-2-1993 that the Bench
committed mistake in thinking that the umpire granted pendente lite
interest and is a mistake of fact and law but had confirmed the pendente
lite interest on its power. Thus these two appeals, with a delay of 137
days in filing the appeal against original judgment. The delay is
condoned.
(3.) The learned Solicitor General contended that the Division Bench having held that the umpire committed illegality in awarding damages twice over
on claims 11 and 12, though the contractor was entitled to damages only
in respect of one claim, committed manifest error of law in upholding the
entire award. The fact that the umpire had committed illegality in
awarding damages twice over would indicate his non-application of
judicious mind to the claims in an objective manner. In a non-speaking
award it is difficult to decide how he adjudged the claims. Thereby he
committed misconduct which entails the setting aside of the award as a
whole and the doctrine of severability becomes inapplicable to the facts
of this case. His next contention was that under clause 62 of the general
conditions, certain matters were to be finally determined by the Railways
and the arbitrator lacked jurisdiction to decide these claims and thereby
the award gets vitiated by manifest illegality on its face. There was
sufficient time for the arbitrator, even after the extended time to make
the award in respect of the counter-claim. But was not done, which would
also prove the non-application of judicious mind in an objective and
dispassionate manner and thereby the award gets vitiated by misconduct
committed by the umpire. The 3rd contention is that the court lacked
power to award pendente lite interest by operation of Section 29 of the
Act. Shri Soli Sorabjee, the learned Senior Counsel for the
respondent-contractor contended inter alia that though the award is a
non-speaking award since the umpire granted each claim separately, the
claims on items 11 and 12 are severable from the rest of the award. The
High Court upheld the highest of the two claims granted by the umpire.
The claim for loss of profits on item 11 and for damages on item 12 are
distinct and separate concepts. The umpire, therefore, was justified to
grant separate amounts on each of the claims which would show active
consideration and application of the mind. Hence it is Dot a misconduct.
Even otherwise they are severable from the rest of the award, which could
be sustained. The grant of pendente lite interest by arbitrator was not a
settled principle till the Constitution Bench decision of this Court in
Secretary, Irrigation Department v. G. C. Roy, 1991(1) SCC 508 was
rendered. Earlier Division Bench of this Court in Executive Engineer
(Irrigation) v. Abhaduta Jena, 1988(1) SCR 253 where it was held that
arbitrator had no power to award interest pendente lite, was overruled.
In this twilight zone of law, the arbitrator did not award interest
pendente lite. In view of the Constitution Bench judgment in G. C. Roy
case, the grant of pendente lite interest by the court is legal. Even
otherwise if this Court finds that the High Court committed illegality in
granting interest pendente lite the matter requires remittance to the
umpire, for fresh decision in this behalf. Similarly on the
counter-claim, it was contended, that no counter-claim in fact was laid,
although belatedly a counter-statement was made, as found by the umpire.
This point was not argued before the Single Judge nor seriously disputed
before the Division Bench. Even otherwise, this dispute also could be
remitted to the umpire for reconsideration.;
Click here to view full judgement.
Copyright © Regent Computronics Pvt.Ltd.