JUDGEMENT
-
(1.)On an application preferred by the respondent herein under
Section 11(6) of the Arbitration and Conciliation Act, 1996
(hereinafter referred to as the Act), the High Court has
appointed/nominated an Arbitrator on behalf of the appellant herein on
the ground that in spite of notice by the respondent in this behalf,
the appellant had failed to nominate its Arbitrator in terms of Clause
25 of the Agreement entered into between the parties. Since the
respondent had already nominated its Arbitrator, further direction is
given that the two Arbitrators (one nominated by respondent and one
appointed by the Court for the appellant), shall appoint an Umpire in
consonance with the said Clause 25. This order is impugned by the
appellant primarily on the ground that Clause 25 was modified by three
supplementary agreements whereby the entire edifice of the said
arbitration clause stood adhered and on a conjoint reading of original
Clause 25 with modification effected by the supplementary agreements,
there was no question of arbitration between the appellant and the
respondent at this stage. To appreciate this contention, one will have
to traverse through the relevant clauses of the main contract as well
as supplementary agreements. Thus, we would like to state along with
the events, as they occurred, in chorology. In fact, as we proceed to
unfurl the events with our comments thereon, there and then we shall
be getting answer as well to the issue involved.
(2.)An agreement dated 29.2.1988 was entered into between the
Standing Conference of Public Enterprises (SCOPE) and the appellant
namely Larsen & Toubro (L&T Ltd.). This agreement was for construction
of Twin Tower Office Complex at Laxmi Nagar District Centre, Delhi
which was awarded by the SCOPE to the appellant. Original contract
value for this work was stipulated at Rs.27.48 Crores. Works comprised
of the Civil Works and also subsidiary works, that could be ordered
from time to time by SCOPE/Architect. This agreement also permitted
the appellant to sub-contract. Accordingly, the appellant entered into
an agreement dated 3.3.1988 with the respondent. While retaining the
civil works with itself, the appellant awarded finishing works
including brickworks, wood works, flooring, furnishing, aluminum works
and other miscellaneous works including waterproofing etc. to the
respondent. It was a pass through contract on a back to back basis.
The value of sub contract was stated as Rs.12.08 crores. Clause 2 of
this agreement dated 3.3.1988 pertains to the payments which were to
be made by the appellant to the respondent. As can be seen from the
reading of this Clause, as reproduced below, amount under this sub
contract was payable to the respondent by the appellant only on
receipt of corresponding receipts from SCOPE:
"Clause 2 L&T shall pay "MHB" the said contract amount or such
other sum as shall become payable only as and when the said
payments are received by "L&T" from SCOPE at the time and in the
manner hereinafter specified in the terms and conditions of this
Contract."
(3.)Another important stipulation in this sub contract was Clause 6,
as per which the respondent was to perform the work awarded to it to
the satisfaction of SCOPE, namely the Principal. It reads as under:
"Clause 6 All obligations in respect of ancillary works
undertaken by MHB shall be performed by MHB itself and will not
jeopardize the interest and contract of L&T with SCOPE.
Satisfaction of SCOPE, their representatives and Architects
shall form the basis of this agreement."
Click here to view full judgement.
Copyright © Regent Computronics Pvt.Ltd.