APARNA A. SHAH Vs. SHETH DEVELOPERS PVT. LTD.
LAWS(SC)-2013-7-18
SUPREME COURT OF INDIA (FROM: BOMBAY)
Decided on July 01,2013

Aparna A. Shah Appellant
VERSUS
SHETH DEVELOPERS PVT. LTD. Respondents

JUDGEMENT

- (1.) Leave granted.
(2.) This appeal is directed against the final judgment and order dated 24.09.2010 passed by the High Court of Judicature at Bombay in Criminal Writ Petition No. 1823 of 2010 whereby the High Court partly allowed the petition filed by the appellant herein.
(3.) Brief facts: a) M/s Sheth Developers Private Ltd.-the respondent herein is a company incorporated under the provisions of the Companies Act, 1956 having its registered office at 11, Vora Palace, M.G. Road, Kandivali (West), Mumbai and is engaged in the business of land development and constructions. Aparna A. Shah (the appellant herein) and Ashish Shah, her husband, are the Land Aggregators and Developers who have been in the said business for the last 15 years and are the owners of certain lands in and around Panvel. b) According to the appellant, in January 2008, since the Company was interested in developing a Township Project and a Special Economic Zone (SEZ) project in and around Panvel, Dist. Raigad, Maharashtra, one Virender Gala of Mahavir Estate Agency - the Broker, introduced them to the appellant herein and her husband as the land owners holding huge land in Panvel. The appellant represented to the Company that the said land was ideal for the development of a Township Project and a Special Economic Zone (SEZ) and also that they have no financial means and capacity to develop the same single handedly. It was further represented that they were also looking for a suitable person, interested in developing the said land jointly with them. (c) On believing the above said representations, the respondent-Company agreed for the development of the said land jointly with the appellant herein and her husband. When the respondent-Company requested for inspection of the title documents in respect of the said land, the appellant and her husband agreed for the same upon the entrustment of a token amount of Rs. 25 crores with an understanding between the parties that the said amount would be returned if the project is not materialize. Agreeing the same, the respondent-Company issued a cheque of Rs. 25 crores in favour of the appellant herein and her husband. However, for various reasons, the proposed joint venture did not materialize and it was claimed by the appellant herein that the whole amount of Rs. 25 crores was spent in order to meet the requirements of the initial joint venture in the manner as requested by the respondent-Company. (d) According to the appellant, again the respondent-Company expressed interest to start a new project and to take financial facilities from their bank in order to submit a tender for the purchase of a mill land. With regard to the same, the respondent-Company approached the appellant herein and her husband and informed that they are not having sufficient securities to enable the bank to grant the facility and the bank is to show receivables in writing. Therefore, on an understanding between the respondent and the appellant, a cheque of Rs. 25 crores was issued by the husband of the appellant from their joint account. It is the case of the appellant that in breach of the aforementioned understanding, on 05.02.2009, the respondent deposited the cheque with IDBI Bank at Cuffe Parade, Mumbai and the said cheque was dishonoured due to "insufficient funds". e) On 18.02.2009, a statutory notice under Section 138 of the Negotiable Instruments Act, 1881 (in short 'the N.I. Act") was issued to the appellant and her husband asking them to repay the sum of Rs. 25 crores. On 06.03.2009, the appellant and her husband jointly replied mentioning the circumstances in which the said cheque was issued with the supporting letters. f) On 04.04.2009, a complaint was filed against the appellant and her husband in the Court of the Metropolitan Magistrate, Dadar, Mumbai and the same was registered as Case No. 1171-SS of 2009. By order dated 20.04.2009, process was issued against them. g) On 12.01.2010, the appellant and her husband filed an application objecting the exhibition of documents and the same was registered as Exh. 28. By order dated 11.05.2010, the said application was dismissed. h) Against the issuance of process dated 20.04.2009 and order dated 11.05.2010 dismissing the application by the Magistrate, the appellant filed Writ Petition No. 1823 of 2010 before the High Court. The High Court, by impugned order dated 24.09.2010, partly allowed the petition and quashed the order dated 11.05.2010 and directed the Magistrate to decide the objections raised by the counsel for the accused after hearing both the sides, but refused to quash the proceedings. i) Aggrieved by the said order, the appellant has filed the above appeal by way of special leave.;


Click here to view full judgement.
Copyright © Regent Computronics Pvt.Ltd.