JUDGEMENT
-
(1.) These appeals have been preferred against the impugned judgment
and order dated 30.7.2002 passed by the High Court of Rajasthan
(Jaipur Bench) in Civil Writ Petition Nos. 5481/1994 and 105/1997, by
which the High Court has allowed the writ petitions filed by the
respondent-Diamond and Gem Development Corporation Ltd. (hereinafter
referred to as the 'Company'), for quashing the order of cancellation
of allotment of land and directing the appellants for providing the
approach/access road.
(2.) As these appeals have been preferred against the common impugned
judgment, for the sake of convenience, Civil Appeal Nos. 7252-53/2003
are to be taken to be the leading case. The facts and circumstances
giving rise to these appeals are :
A. That a huge area of land admeasuring 607 Bighas and 5 Biswas
situate in the revenue estate of villages Durgapura, Jhalan Chod,
Sanganer and Dhol-ka-Bad in District Jaipur, stood notified under
Section 4(1) of the Rajasthan Land Acquisition Act, 1953 (hereinafter
referred to as the 'Act') on 18.7.1979, for a public purpose i.e.
industrial development, to be executed by the appellant Rajasthan
State Industrial Development and Investment Corporation (in short
'RIICO').
B. Declaration under Section 6 of the Act was made on 22.6.1982 for
the land admeasuring 591 Bighas and 17 Biswas. After meeting all
requisite statutory requirements contained in the Act, possession of
the land, was taken over by the Government and was subsequently handed
over to appellant-RIICO, on 18.10.1982 and 17.11.1983. The Land
Acquisition Collector assessed the market value of the land and made
an award on 14.5.1984. RIICO made allotment of land admeasuring 105
acres vide allotment letter dated 10.3.1988 to the respondent no.1
company, to facilitate the establishment of a Gem Industrial Estate
for the manufacturing of Gem stones.
C. In pursuance of the aforesaid allotment letter, a lease deed was
executed between the appellant and respondent-company on 22.5.1989,
with a clear stipulation that the land was allotted on an "as is-where-
is", and that the respondent-company must complete the said project
within a period of 5 years, and further that, in the event that the
terms and conditions of the lease agreement were not complied with,
the appellant would be entitled to recover its possession in addition
to which, various other conditions were also incorporated therein.
D. After possession was taken by the respondent-company,
construction could be carried only on a portion of the land allotted
to it. As the development work was being carried out at an extremely
slow pace, the appellant issued various notices from time to time,
reminding the respondent-company that it was under an obligation to
complete the project within a specified period, owing to which, it
must accelerate work. Additionally, there also arose some difficulty
with respect to the respondent-company's attempts to sub-lease the
said premises, or parts thereof, and in view of this, an amendment
dated 4.11.1991 was inserted in Rule 11-A of the Rajasthan Land
Revenue (Industrial area Allotment) Rules, 1959 (hereinafter referred
to as the 'Rules 1959'), enabling the company to sub-lease the said
land.
E. The appellant vide notice dated 4.7.1992, informed the
respondent-company, that as per clause 2(n) of the lease deed, all
construction had to be completed within a stipulated time period of 5
years. The respondent-company began asking the appellant to provide
it accessibility via road, from the Jaipur Tonk main road and, as the
same was not provided, the respondent-company filed Writ Petition No.
5481 of 1994 before the High Court, seeking the issuance of a
direction to the appellant to provide to it, the aforesaid road.
F. During the pendency of the aforesaid writ petition, the
appellant expressing its dis-satisfaction with regard to the progress
of the development of the said land by the respondent-company, filed a
reply to the said writ petition before the High Court stating that it
was not under any obligation to provide to the respondent-company the
aforementioned approach road, as the lease deed had been executed
between them, on the basis of an "as-is-where is" agreement. Further,
the appellant issued a show cause notice dated 29.8.1996, to determine
the lease in light of the lease agreement, in lieu of the fact that
the respondent-company had not made any progress regarding the
completion of the project, and even after the expiry of a period of 5
years, only 10% of the total construction stood completed. In
pursuance thereof, the lease deed was cancelled vide order dated
1.10.1996, and possession of the land in dispute was taken back by the
appellant on 3.10.1996.
G. The respondent-company filed another Writ Petition No. 105 of
1997, challenging the cancellation order dated 1.10.1996 and the
taking over of possession by the appellant on 3.10.1996. The appellant
contested the said writ petition on the grounds that it was entitled
to restoration of possession, as the respondent-company had failed to
ensure compliance with the terms and conditions incorporated in the
lease deed, according to which, the company was required to complete
the said project within a period of 5 years. However, presently, the
extent of development completed by it stood at 10%. Therefore, in
light of the aforementioned circumstances, the appellant had no choice
but to cancel the lease deed and take back possession.
H. The High Court vide its impugned judgment and order, allowed
both the writ petitions quashing the order of cancellation, and
directed the restoration of possession of the aforesaid land to the
respondent-company, and further, also directed the appellant to
provide to the respondent-company, the approach/access road demanded
by it.
Hence, these appeals.
(3.) Shri Dhruv Mehta, learned senior counsel appearing on behalf of
the appellant-RIICO, and Shri Manish Singhvi, learned Additional
Advocate General for the State of Rajasthan have submitted that, as
the allotment of the land had been made to the respondent-company on
an 'as-is-where-is" basis, there was no obligation on the part of
RIICO to provide to it, the said access road. The terms of the
contract must be interpreted by court, taking into consideration the
intention of the parties and not on the basis of equitable grounds.
Moreover, the cancellation of the deed was in accordance with the
terms and conditions incorporated in the lease deed, and therefore, in
light of the facts and circumstance of the case, the High Court has
committed an error, by quashing the order of cancellation and, in
issuing a direction for the restoration of possession and for the
provision of the access road.
The High Court has mis-interpreted the amendment to Rule 11-A of
the Rules 1959, and has thus held that the appellant had no
jurisdiction to cancel the said lease, as the respondent-company by
virtue of the operation of the amended provision, had become a direct
lessee of the State. In such a fact-situation, there was no obligation
on the part of the appellant to provide the approach road as it was
not the lessor of the respondent-company. In case by virtue of the
amendment in Rule 11-A of the Rules 1959, the State Government became
the lessor, the appellant-RIICO lost the title/interest over the
property which had been acquired by it on making payment of the huge
money and that too, without getting any refund. Such an interpretation
leads to absurdity. Thus, the appeals deserve to be allowed.
;