JUDGEMENT
-
(1.) The Special Leave Petition and the application
filed on behalf of the Respondents for early hearing
and disposal of the Special Leave Petition were taken
up together for consideration. The facts on which theSpecial Leave Petition is based, are set out
hereinbelow.
(2.) By its letter of acceptance No.NHAI/PH
11/NHDP/ADB/GM-11/NS1/746 dated 30
th
December, 2005, the
National Highways Authority of India, hereinafter
referred to as NHAI , awarded a contract to the
Respondent, SSANG YONG Engineering & Construction Co.
Ltd., for the National Highways Sector II Project,
Package-ADB-II/C-8, which involved the four laning of
Jhansi-Lakhadon sector KM 297 to KM 351 of National
Highway 26 in the State of Madhya Pradesh. The total
contract amount for the aforesaid project was more than
Rs. 750 crores. An agreement was entered into by the NHAI
with the Petitioner on 13
th
August, 2006. Clause 27 of
the Agreement incorporated an arbitration clause
stipulating that all disputes and differences arising
out of or in connection with the Agreement dated 13
th
August, 2006, would be referred to arbitration to be
conducted in English in Singapore in accordance with
the Singapore International Arbitration Centre (SIAC)Rules. For the purpose of reference, Clause 27 of the
Agreement relating to arbitration is extracted
hereinbelow :
"27. Arbitration
27.1 All disputes, differences arising out of
or in connection with the Agreement shall be
referred to arbitration. The arbitration
proceedings shall be conducted in English in
Singapore in accordance with the Ssangyong
International Arbitration Centre (SIAC) Rules
as in force at the time of signing of this
Agreement. The arbitration shall be final and
binding.
27.2 The arbitration shall take place in
Singapore and be conducted in English language.
27.3 None of the Party shall be entitled to
suspend the performance of the Agreement merely
by reason of a dispute and/or a dispute
referred to arbitration."
(3.) According to Clause 1 of the Agreement read with
the Appendix thereof, the Petitioner was to provide all
adequate manpower, material, plant, machinery,
construction equipment and all other resources,
including finance, which would be required to perform
the work Bank Guarantee was furnished by the Petitioneron 31
st
October, 2006, whereby the Bank undertook to pay
to the Respondent on its first written demand and
without cavil or argument any sum or sums within the
limits of Rs. 6,05,00,000/-, without there being need to
prove or give any reasons for the demand for the said
sum. The guarantor also waived the necessity of the
Respondent Company making a demand for the debt to the
contractor/petitioner before presenting the demand. The
guarantor also agreed that no change or addition or
other modification of the terms of the contract or of
the work to be performed thereunder or any of the
contract documents, which may be made between the
Respondent and the Petitioner, would release the Bank
from its liability under the Agreement. Similarly,
three Bank Guarantees of Rs. 1 crore each and one Bank
Guarantee for Rs. 3 crores were also furnished to secure
mobilization advance.;
Click here to view full judgement.
Copyright © Regent Computronics Pvt.Ltd.