JUDGEMENT
-
(1.) Leave granted.
(2.) Pursuant to the agreement between the parties
being agreement No. 11 of 1989-90 concerning
construction of residential complex at Shimla, certain
disputes arose. As per the terms of the contract, the
Arbitrator was appointed to adjudicate the claims of
the respondent and counter-claims of the appellants.
On August 12, 1998, the Arbitrator passed the award.
Aggrieved thereby, the appellants filed objections
under Section 34(3) of the Arbitrator and Conciliation
Act, 1996 (for short "the Act"). The objections were
accepted by the High Court to the extent that the
reasons were not given by the Arbitrator and,
accordingly, the matter was sent back to the
Arbitrator for giving reasons in support of the award.
(3.) After remand, the Arbitrator considered the
matter and passed the award on February 14, 2001.
The appellants filed objections against the award dated
February 14, 2001. They also deposited the entire
amount due under the award before the High Court on May
24, 2001. The objections filed by the appellants were
ultimately rejected by the single Judge of the High
Court on February 26, 2008. Against this order, intracourt appeal is said to be pending. The respondent,
however, started execution of the Award dated February
14, 2001 by filing Execution Petition on August 12,
2008. The appellants filed objections to the Execution
Petition.;
Click here to view full judgement.
Copyright © Regent Computronics Pvt.Ltd.