JUDGEMENT
-
(1.) This Appeal, by special leave, arises from
the judgment and order dated November 25, 2002 passed by
the Punjab & Haryana High Court.
(2.) The controversy arises in this way. A
contract was entered into between the appellant M/s Ladli
Construction Co. (P) Ltd. (hereinafter referred to as 'the
Contractor'), and the respondent Nos. 1 and 2, namely,
Punjab Police Housing Corporation Limited and Executive
Engineer (Civil), Punjab Police Housing Corporation
Limited (hereinafter referred to as 'the Corporation') for
construction of 240 houses Type II-A at Urban Estate,
Ludhiana at an estimated cost of Rs. 273.84 Lakhs. The
contract provided in Clause 2 that time was essence of the
contract and the time allowed for carrying out work as
entered in the tender shall be strictly observed by2
Contractor. The Contractor could not maintain the time
schedule and the progress of the work was not observed. The
Contractor was directed to push up the progress of work but
that also it failed to do. The Contractor was notified
that if it failed to take any action to show requisite
progress by 30th of April, 1991, action against it under
Clause 3 of the agreement would be taken. Still there was
no requisite progress in execution of the work by the
Contractor. On May 8, 1991, the Corporation resorted to
action under Clause 3 of the contract, rescinded the
contract and adopted further course by giving unexecuted
work to another contractor. The disputes, thus, having
arisen between the parties, the Contractor moved the court
of Sub Judge, First Class, Chandigarh, for appointment of
the arbitrator in terms of Clause 25A of the contract.
(3.) On the application made by the Contractor for
appointment of the arbitrator, the Sub Judge, on May 13,
1992, ordered that matter in dispute may be referred for
arbitration as per Clause 25A of the agreement and,
accordingly, as per the agreement and the statement of
parties, the Sub Judge ordered the Chief Engineer of the
Corporation to act as an arbitrator as provided under
Clause 25A of the agreement. Both the parties were
permitted to file claim and counter claim before the
arbitrator.;
Click here to view full judgement.
Copyright © Regent Computronics Pvt.Ltd.