LADLI CONSTRUCTION CO P LTD Vs. PUNJAB POLICE HOUSING CORPN LTD
LAWS(SC)-2012-2-62
SUPREME COURT OF INDIA (FROM: PUNJAB & HARYANA)
Decided on February 23,2012

LADLI CONSTRUCTION CO. (P) LTD. Appellant
VERSUS
PUNJAB POLICE HOUSING CORPN. LTD. Respondents

JUDGEMENT

- (1.) This Appeal, by special leave, arises from the judgment and order dated November 25, 2002 passed by the Punjab & Haryana High Court.
(2.) The controversy arises in this way. A contract was entered into between the appellant M/s Ladli Construction Co. (P) Ltd. (hereinafter referred to as 'the Contractor'), and the respondent Nos. 1 and 2, namely, Punjab Police Housing Corporation Limited and Executive Engineer (Civil), Punjab Police Housing Corporation Limited (hereinafter referred to as 'the Corporation') for construction of 240 houses Type II-A at Urban Estate, Ludhiana at an estimated cost of Rs. 273.84 Lakhs. The contract provided in Clause 2 that time was essence of the contract and the time allowed for carrying out work as entered in the tender shall be strictly observed by2 Contractor. The Contractor could not maintain the time schedule and the progress of the work was not observed. The Contractor was directed to push up the progress of work but that also it failed to do. The Contractor was notified that if it failed to take any action to show requisite progress by 30th of April, 1991, action against it under Clause 3 of the agreement would be taken. Still there was no requisite progress in execution of the work by the Contractor. On May 8, 1991, the Corporation resorted to action under Clause 3 of the contract, rescinded the contract and adopted further course by giving unexecuted work to another contractor. The disputes, thus, having arisen between the parties, the Contractor moved the court of Sub Judge, First Class, Chandigarh, for appointment of the arbitrator in terms of Clause 25A of the contract.
(3.) On the application made by the Contractor for appointment of the arbitrator, the Sub Judge, on May 13, 1992, ordered that matter in dispute may be referred for arbitration as per Clause 25A of the agreement and, accordingly, as per the agreement and the statement of parties, the Sub Judge ordered the Chief Engineer of the Corporation to act as an arbitrator as provided under Clause 25A of the agreement. Both the parties were permitted to file claim and counter claim before the arbitrator.;


Click here to view full judgement.
Copyright © Regent Computronics Pvt.Ltd.