JUDGEMENT
-
(1.) This appeal is directed against the judgment and order dated 20th
July, 2006 passed by the High Court of Uttaranchal at Nainital whereby the
decree passed by the learned trial court under the Arbitration Act, 1940
(hereinafter referred to as 'the Act') has been modified. The terms of
award as passed by the learned Arbitrator and the decree passed by the
learned trial court as well as the modification thereof by the High Court
will now have to be noticed :
(2.) The appellants and the respondent herein had entered into a contract
for execution of certain works in connection with the Tehri Hydro Dam
Project. The agreement between the parties was executed on 29th March,
1978 and the works in question were completed on 31st December, 1985. The
completion certificate was issued by the competent authority of the
appellant-Corporation on 27th April, 1986. As the final bill of the
respondent-contractor had not been prepared and security money, furnished
by way of bank guarantee was not released, the parties went to arbitration
in accordance with the Arbitration clause under the contract/agreement. In
the course of the aforesaid Arbitration proceeding the appellant-
Corporation submitted a final bill which according to the respondent-
Contractor entitled it to receive a sum of Rs.10,17,461.09 on account of
work done besides a sum of Rs. 12.50 lakhs that was lying in deposit with
the Corporation. As the amounts due. according to the respondent-
contractor, had become crystallized, another arbitration proceeding between
the parties for the aforesaid specific claims commenced in accordance with
the arbitration clause of the agreement.
(3.) The award in the aforesaid arbitration proceeding was passed on 29th
January, 1996 holding the respondent contractor to be entitled to the sum
of Rs. 10,17,461/- with the interest at the rate of 6% per annum from the
date of invocation of the claim till the date of the award and at the rate
of 12% per annum from the date of the award till payment or till the
award is made Rule of court, whichever is earlier. Insofar as the claim
of the respondent contractor to the sum of Rs. 12.50 lakhs lying in
deposit with the Corporation, the Arbitrators held the said amount to be
beyond the scope of the dispute raised in the arbitration proceeding.
Accordingly, the respondent contractor was left with the option of
settling the said claim in an amicable manner or by resorting to a civil
suit for recovery of the same.;
Click here to view full judgement.
Copyright © Regent Computronics Pvt.Ltd.