JUDGEMENT
-
(1.) The questions which arise for consideration in this appeal are whether the
Government of NCT of Delhi could have invoked Section 17(1) and (4)
of the Land Acquisition Act, 1894 (for short, the Act ) and dispensed
with the rule of hearing embodied in Section 5A(2) thereof for the
purpose of acquiring land measuring 80 bighas 15 biswas including 21
bighas 3 biswas belonging to the appellants for a public purpose, namely,
establishment of electric sub-station by Delhi Transco Limited (for short,
DTL ) at village Mandoli and whether the Division Bench of the Delhi
1High Court had rightly negatived the appellants challenge to the
acquisition of their land.
(2.) For deciding the aforesaid questions, it will be useful to notice the events
which led to the issue of notification dated 13.10.2009 under Section 4(1)
read with Section 17(1) and (4) of the Act and declaration dated
9.11.2009 under Section 6(1) of the Act.
2.1 It is not clear from the pleadings of the parties and the record produced
before the High Court and this Court as to when the decision was taken to
establish 400/220 KV sub-station at East of Loni Road but this much is evident
that by a communication sent in August, 2004, the DTL requested the Delhi
Development Authority (for short, the DDA ) for allotment of land. For the
next about 10 months nothing appears to have happened. Between June and
October, 2005 different functionaries of DTL made some correspondence interse in the matter of establishment of the sub-station. On 5/6.12.2005, Manager
(400/220 KV SS&L) sent a communication to the Commissioner (Planning),
DDA wherein he emphasized that establishment of the sub-station was
necessary to meet the power demand of East Delhi and particularly the
upcoming Commonwealth Games. In his reply dated 8.2.2006, Joint Director
(MP), DDA informed the DTL that allotment of sites suggested by it is not
feasible because site A was developed as a park and site B was earmarked as
a community centre.
2.2 Between January, 2006 and July, 2008, the officers of the DTL, the DDA
and the Government of N.C.T. of Delhi exchanged letters on the issue of
allotment of land for the sub-station. While the officers of DTL stressed the
need for early allotment of land, the officers of the DDA repeatedly expressed
their inability to allot the particular site by pointing out that the same was
reserved for other purpose. On 28.07.2008, Secretary (Power), Government of
NCT of Delhi-cum-CMD, DTL requested the DDA to change the land use of
the particular site and inform the Government of N.C.T. of Delhi so that action
could be taken for the acquisition of land under Section 17 of the Act. In that
letter, it was also mentioned that due to paucity of land, the DTL has proposed
to establish a GIS indoor type sub-station which could be accommodated in a
space of about 200 x 125 meters as against the original requirement of 700 x
500 meters. The relevant portions of that letter are extracted below:
In pursuance of above, a meeting was held with ViceChairman, DDA on 06.05.2008 wherein a request was made
for the allotment of land in East Delhi. Officers of Delhi
Transco Limited, State Transmission Utility, along with
Officers of DDA and the concerned ADM of the area had
identified the land in their joint inspection held on 30
th
June,
2008. Copy of Khasra Nos. and their Report is enclosed as
Annexure-I. However, in the meantime DDA informed that
the land in question is not acquired by DDA. It was further
informed that as per Master Plan, Agriculture/Green area
can be utilized for Utilities. Copy of the letter No.
F.6(4)2004/MP/D-127 dated 19.5.2008 is enclosed as
Annexure-II. Since the establishment of the Grid Station is
of paramount importance for strengthening the power supply
in East Delhi, DDA is requested to change the land use and
to inform GNCTD so that action be taken for acquisition of
the same under Section 17, i.e., for the public utility.
Earlier it was proposed to construct an outdoor 400/200 KV
Grid Station but keeping in view the paucity and availability
of land DTL has now proposed to establish a GIS indoor
type sub-station which could be accommodated in a space of
about 200 x 125 meters. It shall be appreciated if appropriate
directions are issued to the concerned officers for doing the
needful expeditiously.
2.3 After about one month, Joint Secretary (Power) sent communication
dated 9.9.2008 to the Principal Secretary, Land and Building Department with
the request that action may be initiated for the acquisition of the identified piece
of land by invoking Section 17 of the Act. The relevant portions of that letter
are extracted below:
Hon ble Prime Minister of India has laid the foundation
for 1500 KV gas based power plant at Bawana on
24.03.2008 being constructed by Pragati Power
Corporation Limited, a company owned by Govt, of NCT
of Delhi in order to evacuate and utilize the generation
from this plant for the benefit of Delhi, a study was
conducted by Central Electricity Authority which has
recommended the establishment of a 220 KV substation
in East Delhi for evacuation of power.
Officers of Delhi Transco Limited along with officers of
DDA and concerned ADM have identified the land
measuring 200 M x 150 M in East Delhi for the proposed
grid. Copy of Khasra Nos. and their report is enclosed at
Annexure-1. Sketch showing broad location of the plot
proposed to be acquired with Khasra Nos. of the
proposed location is at Annexure-II. DDA has informed
that the land in question is not acquired by DDA.
However, as per Master Plan 2021, public utilities are
permitted in all use zones. In this regard, a copy of
Director (Planning) DDA letter dated 19.05.2008 is
enclosed as Annexure-III. The proposed site has already
been taken up with VC, DDA for change of land use
(Annexure-IV).
The commissioning of 155 MW power plant at Bawana
is scheduled before the Commonwealth Games in
October-2010. Therefore, keeping in view the urgency
involved, kindly initiate the process for acquisition of
identified peace of land in East Delhi in favour of
Department of Power, GNCTD as provided under section
17 of the Land Acquisition Act at the very earliest.
Soon thereafter, the Land and Building Department sent letter dated 30.9.2008
to Additional District Magistrate-cum-Land Acquisition Collector (North-East)
to send the following information/documents:
1. Draft notification u/s 4, 6 and 17 along with the copy of Aks Sizra,
field book etc.
2. Report after conducting Joint Survey.
3. 80% estimated compensation amount with Calculation Sheet.
52.4 After about six months, Deputy General Manager (Planning-I), DTL sent
letter dated 6.3.2009 to Deputy Secretary (Land Acquisition) and informed him
that land measuring 250 x 200 sq. mts. with approach road will be required to
accommodate the proposed three voltage level equipment as against the
requirement of 200 x 125 sq. mts. indicated in the earlier communications. The
concerned officer also requested that the acquisition of 80 bighas 15 biswas
land may be finalized as per the joint site inspection carried out on 12.01.2009.
2.5 On its part, the DDA sent letter dated 8.5.2009 to the Deputy Secretary
(Land Acquisition) that a joint site inspection be carried out for finalization of
the site. However, the latter sent communication dated 16.6.2009 to the DDA
to issue NOC required for initiation of the acquisition proceedings.
2.6 In September, 2009, the Land and Building Department of the
Government of NCT of Delhi prepared proposal for the acquisition of land
measuring 200 x 125 sq. mts. by invoking Sections 4 and 6 read with Section
17(1) and (4) of the Act. This is evident from the notings recorded in
paragraphs 56 to 61 and 63 to 65 of file bearing No. F.S(11)/08/L&B/LA,
which are extracted below:
56. A requisition was received from Joint Secretary (Power)
Department of Power for acquisition of land measuring 200 x
125 Sq. m. identified in East Delhi for construction of 400 x
200 KV grid station (Village Mandoli) vide their letter No.
F.11(88)/2008/Power/2186 dated 09.09.2009 (P-6/C).
Accordingly, the ADM/LAC (NE) was requested for draft
notifications and other revenue records vide letter dated
30.09.2008 (P-7/C).
57. The ADM/LC (NE) vide his letter dated 31.01.2009 (P-
28/C) forwarded draft notification u/s 4 & 6 (P-26 & 27/C) for
acquisition of land measuring 80 Bigha 15 Biswa. Copy of Joint
Survey Report (P-23/C), copy of Field Book (P-20/C), copy of
Asks Sizra (P-19/C) and Calculation Sheet for estimated
compensation amount (P-25/C).
58. The revenue staff scrutinized the draft notification and
some discrepancies have been found. The report of revenue
branch may be seen at page (P-5 & 6/N).
59. Accordingly, LAC (NE) was requested for clarification
vide letter dated 2/3/09 (page-29/C). A clarification was given
by LAC (NE) in aforesaid context and may be seen at P-32 to
39/C. Report of revenue branch may be seen at page 11 &
12/N. Letter dated 30/7/08 and 6/3/09 received from Delhi
Transco Ltd. regarding change of proposal may be seen at P.30
and 31/C. Delhi Transco Ltd. has given the justification for the
change of proposal regarding requirement of land, i.e., 80
Bigha 15 Biswa instead of 200 x 125 Sq.m.
60. Vide letter No.F.6(4)2004-MP/265 dated 7/9/09 Jt.
Director (MP) DD has informed that DDA has no objection
with respect to proposed location of land for establishing
400/200 KV ESS subject to compliance of the following
conditions:-
a. Submission of a layout plan/location plan with
description of the land under reference be submitted to
ascertain the boundaries of the site.
b. Justification for an area of 6.8 hact. against 2.96 hact.
required for establishment of 200/400 KV ESS as per
MPD-2021 norms.
c. This is a Master Plan level utility for which change of
land use will be processed after land is acquired.
d. Submission of transmission route alignment plan as the
surrounding area is thickly populated.
e. The site shall not be used for any other purpose other
than ESS.
61. As the matter is urgent and related to Commonwealth
Games, if approved Hon ble L.G. may be requested to kindly
approve acquisition of land measuring 80 Bigha 15 Biswa as
per the draft notifications placed opposite for acquisition of
land for establishment of 400 x 200 KV sub-station in villageMandoli and issuance of notification u/s 4 read with 17(4) and
section 6 along with 17(1) of Land Acquisition Act, 1894.
63. May kindly see the proposal at page 21/N regarding
acquisition of land measuring 80 Bigha 15 Biswa for
construction of 400 x 200 KV grid station in village Mandoli.
The proposal has been received from Power Department, Govt.,
of NCT of Delhi, which is available at page 6/C. It has been
mentioned in the proposal that Hon ble Prime Minister of India
has laid the foundation stone for 155 MW gas based power
plant at Bawana on 24-3-2008 which is being constructed by
Pragati Power Corporation Limited, a company owned by
Govt., of NCT of Delhi. It has been also mentioned in the
proposal that to evacuate and utilize the generation from this
plant for the benefit of Delhi, a study was conducted by Central
Electricity Authority which has recommended the
establishment of a 220 KV sub-station in East Delhi for
evacuation of power. The Power Department has requested that
the acquisition of the above said land may be proceeded with
under the emergency provisions of the Land Acquisition Act
because 1500 MW power at Bawana is scheduled to be
commissioned before the Commonwealth Games, 2010.
64. The Land Acquisition Collector (N/E) has prepared a
draft notification under section 4 & 6 (page 26 & 27/C) after
conduction the Joint survey report along with concerned
department and copy of the same is available at page 23/C
along with relevant records. As per the joint survey available at
page 22/C and 23/C it appears that entire land is laying vacant
except to Bhattas (Brick Kiln) and boundary walls in 3 Khasras.
The DDA has also provided no objection for acquisition subject
to certain conditions as mentioned in letter dated 07-09-09,
which is available at page 64/C.
65. From the proposal of the Power Department it is clear
that land is required for valid public purpose and urgent need
for acquisition of the land has also been justified by the Power
Department. Therefore, if approved, Hon ble Lt. Governor may
kindly be requested to approve acquisition of land measuring 80
Bigha 15 Biswa as per the draft notification placed opposite for
the public purpose namely for establishing 400 x 200 KV grid
sub-station for Power Department in Village-Mandoli and
issuance of notification u/s 4 read with 17(4) and section 6
along with 17(1) of Land Acquisition Act, 1894.
2.7 The Lieutenant Governor of Delhi accorded his approval on 26.9.2009 in
the following terms:
I have gone through the records and requirement of Delhi
Transco Ltd. for acquisition of land for Establishment of
400x200 kv station at village Mandoli and the draft
notifications prepared by LAC (North-East).
I am fully satisfied that the land measuring 80 Bigha 15 Biswa
is urgently required for above purpose. In view of the urgency
of the scheme, I order that the provisions of section 5A shall not
apply and notifications under section 4 read with 17(4), 6 &
17(1) of the Land Acquisition Act, 1894 be issued immediately.
Sd/-
Tejendra Khanna
Lt. Governor Delhi
26.09.2009.
(3.) In compliance of the direction given by the Lieutenant Governor, the
Government of N.C.T. of Delhi issued notification dated 13.10.2009
under Section 4(1) read with Section 17(1) and (4) for the acquisition of
80 bighas 15 biswas land. The declaration issued under Section 6(1) was
published vide notification dated 9.11.2009. By another notification of
the same date, Land Acquisition Collector (North-East), Delhi was
authorised to take possession of the land on the expiry of 15 days.;